Kolaboro / Desk report from public data: Crown Penang

A real desk report: Crown Penang

Made only from public sources: the official register, the developer's own pages and the press, each with its link. It shows the desk part of a check. A paid check adds what public data cannot show.

Project MYS-004 · developer Ivory Properties Group & Chin Hin Group Property Berhad · Jalan Seri Tanjung Pinang, Tanjung Tokong, George Town, Penang · facts read on or before 13 Nov 2026

Reviewed on 13 Nov 2026 under the review checklist: register Malaysia KPKT TEDUH register. permit 30744-1/07-2027/0684(A)-(S) valid to 2027-07-29; progress 37.50%

Permits and licences

Official site prints developer licence 30744/04-2029/0086(A) (22 Apr 2024 to 21 Apr 2029) and APDL 30744-1/07-2027/0684(A)-(S) (30 Jul 2024 to 29 Jul 2027); both active on TEDUH

  • KPKT TEDUH register lists advertising and sales permit 30744-1/07-2027/0684(A)-(S) for The Crown (30744-1), valid 2024-07-30 to 2027-07-29 Matches the source Source: teduh.kpkt.gov.my
  • Developer Stellar Platinum Sdn. Bhd. holds developer licence 30744/04-2029/0086(A) (valid 2024-04-22 to 2029-04-21); register status Aktif Matches the source Source: teduh.kpkt.gov.my
  • APDL 30744-1/07-2027/0684(A)-(S) active Matches the source Source: teduh.kpkt.gov.my
  • Developer licence 30744/04-2029/0086(A) active Matches the source Source: teduh.kpkt.gov.my

Developer track record

TEDUH lists multiple completed Ivory group projects in Penang with CCC/CFO; Chin Hin Group Property Bhd is Bursa-listed (BusinessToday, StarProperty)

  • JV between Stellar Platinum (Chin Hin Group Property) and Ivory Meadows (Ivory Properties) Matches the source Source: businesstoday.com.my
  • Ivory group has delivered completed projects in Penang Matches the source Source: teduh.kpkt.gov.my

Handover date

  • Vacant possession due 20 Aug 2027 under the first sale agreement (Jadual H, 36 months, first SPA 20 Aug 2024); the register records an approved extension of 18 months to 20 Feb 2029 Matches the source Source: teduh.kpkt.gov.my
  • Target completion December 2028 Contradicted by a source Source: teduh.kpkt.gov.my
  • Completion originally targeted 2027 Matches the source Source: businesstoday.com.my

Construction progress

TEDUH (HIMS 7(f)) reports 37.50%; no progress on the developer site

  • Register shows construction progress of 37.50% (latest 7(f) report in HIMS), overall status "Lancar" (Malay for on track) Matches the source Source: teduh.kpkt.gov.my
  • Construction progress 37.50% Matches the source Source: teduh.kpkt.gov.my

Where buyer money goes

TEDUH records a Jadual H sale agreement (statutory Housing Development Act stage payments into a Housing Development Account); no HDA bank or number on the developer page

  • Buyer money held in a Housing Development Account Not verified Source: crownpenang.com

Plans and unit sizes

Official site shows floor plans for Types A, B, C, D

  • 588 units, 41 floors, RM783,000 to RM2,073,000 Matches the source Source: teduh.kpkt.gov.my
  • Unit sizes 614 to 1,851 sq ft (2023 announcement said 495 to 1,367 sq ft) Contradicted by a source Source: businesstoday.com.my

Promised returns

No guaranteed return; an agent site says the project is 'structured for rental income' without figures

  • Serviced-residence title permits short-term rentals from day one (agent) Not verified Source: thecrown-penang.com

Land title

  • Freehold land, charged to Malayan Banking Berhad Not verified Source: crownpenang.com

Not verified Not checked in this desk report: the land title needs a land office search, which public data does not give.

Contract

Not verified Not read: no contract is public. In a paid check we read yours; the contract reader is free.

Site visit

Not verified Not done: site visits by a local agent are being set up.