Handover slippage by market
For each market: how many months tracked projects are past the first handover date we have on record, among those whose date has passed and that are not recorded as completed. Computed on 18 Nov 2026 from 1,994 projects. A historical statistic from our records, not a forecast and not a verdict about any developer.
Months past the first handover date, per market
| Market | Past the first date | Median months past | Middle half (25th to 75th percentile) | Range | Not yet due | Completed |
|---|---|---|---|---|---|---|
| All markets | 125 | 8 | 5 – 20 | 1 – 107 | 1,549 | 17 |
| Bali | 15 | 8 | 2 – 10 | 2 – 18 | 70 | 2 |
| Dubai | 12 | 5 | 4.3 – 5.8 | 1 – 50 | 466 | 1 |
| Costa del Sol | 9 | 4 | 2 – 8 | 1 – 26 | 21 | 0 |
| Istanbul | 5 | 11 | 11 – 11 | 8 – 11 | 14 | 1 |
Markets with fewer than 5 projects past their first date are counted in "All markets" only. Data as JSON · Data as CSV
Bali n = 15, Median months past 8
Dubai n = 12, Median months past 5
Costa del Sol n = 9, Median months past 4
Istanbul n = 5, Median months past 11
0 – 107
Method
- Projects: every named project we track, except Sumba (our independence policy).
- First date on record: the developer's original handover date where our research recorded one; otherwise the handover date we read first (when two sources were read the same day, the later date, so lateness is not overstated); otherwise the date on record now.
- A year counts from its December, a quarter from its last month, a half from June or December.
- Past the first date: the last month of that date is before the current month and the project is not recorded as completed. Months past = current month minus that month.
- Completed projects are counted but left out of the months: we hold no completion date for them.
- Median and 25th and 75th percentiles: linear interpolation between order statistics (like PERCENTILE.INC in a spreadsheet). Shown for a market from 5 projects.
- Recomputed at the edge whenever our data changes, from /data/named.json, /data/promises.json and /data/bali-cases.json.
Limits
- Dates are what developers and listings published; a misread date changes a figure. Every project page shows its date with the source.
- A project past its first date may be on time against a later date the developer announced; the project page shows both.
- We track projects being marketed now, so finished projects that stopped marketing are under-represented.