Handover slippage by market

For each market: how many months tracked projects are past the first handover date we have on record, among those whose date has passed and that are not recorded as completed. Computed on 18 Nov 2026 from 1,994 projects. A historical statistic from our records, not a forecast and not a verdict about any developer.

Months past the first handover date, per market

MarketPast the first dateMedian months pastMiddle half (25th to 75th percentile)RangeNot yet dueCompleted
All markets12585 – 201 – 1071,54917
Bali1582 – 102 – 18702
Dubai1254.3 – 5.81 – 504661
Costa del Sol942 – 81 – 26210
Istanbul51111 – 118 – 11141

Markets with fewer than 5 projects past their first date are counted in "All markets" only. Data as JSON · Data as CSV

Bali n = 15, Median months past 8

Dubai n = 12, Median months past 5

Costa del Sol n = 9, Median months past 4

Istanbul n = 5, Median months past 11