Construction pace against the registered date
For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.
Updated 23 Nov 2026
A projection from the pace on the register, not a promise, and not a finding about the developer.
Show as a table
| Gap (points) | Projects |
|---|---|
| -60 … -50 | 98 |
| -50 … -40 | 119 |
| -40 … -30 | 168 |
| -30 … -20 | 186 |
| -20 … -10 | 140 |
| -10 … 0 | 94 |
| 0 … 10 | 29 |
| 10 … 20 | 13 |
| 20 … 30 | 9 |
| 30 … 40 | 3 |
| 40 … 50 | 1 |
Projects
| Project | % built (inspection) | Time elapsed | Gap (points) | Pace | Registered completion | Projected range | Register |
|---|---|---|---|---|---|---|---|
| Nad Al Sheba Gardens Phase 10 Shamal · Nad Al Shiba First | 0.4% 20 Aug 2026 | 35% | -34.1 | behind | 1 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Barari Heights SAMANA Developers · Majan, Dubailand | 5.7% 28 Oct 2026 | 40% | -34 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Neem at Park Five Deyaar Development PJSC · Dubai Production City | 15.2% 9 Sept 2026 | 49% | -34 | behind | 1 Dec 2027 | Apr 2033 – Jun 2034 | dubairealestateiq.com |
| The Haven Meraki · Majan | 56.3% 14 Oct 2026 | 90% | -34 | behind | 31 Dec 2026 | May 2028 | dubairealestateiq.com |
| ELAR1S Sky (Elaris Sky) Object 1 · Jumeirah Village Triangle (JVT District 3) | 1.2% 29 Oct 2026 | 35% | -33.8 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Cove Edition 6 Imtiaz Developments · Dubailand Residence Complex | 25.9% 13 Oct 2026 | 60% | -33.8 | behind | 10 Sept 2027 | Jun 2030 – Aug 2030 | dubairealestateiq.com |
| La Tilia at Villanova Phase 1 Dubai Properties · Dubai Land Residence Complex | 13.8% 5 Oct 2026 | 48% | -33.8 | behind | 21 Aug 2028 | Jun 2037 – Dec 2037 | dubairealestateiq.com |
| Helvetia Verde D H G Property Development L.L.C · Bukadra | 0.6% 6 Jul 2026 | 34% | -33.8 | behind | 30 Nov 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Symphony by Chaimaa Deval · Majan | 0% 20 Aug 2026 | 34% | -33.8 | behind | 31 Aug 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Venice 6 Azizi Developments · Madinat Al Mataar | 11.6% 8 May 2026 | 45% | -33.7 | behind | 31 Dec 2027 | Mar 2036 – Oct 2036 | dubairealestateiq.com |
| Hillcrest Nshama · Al Yelayiss 2 | 38.4% 17 Sept 2026 | 72% | -33.7 | behind | 30 Jun 2027 | Dec 2029 | dubairealestateiq.com |
| Nad Al Sheba Gardens Phase 8 & 9 Shamal · Nad Al Shiba First | 0.7% 20 Aug 2026 | 34% | -33.7 | behind | 1 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Rome 2 by Sd SAMANA Developers · Majan | 40.4% 5 Nov 2026 | 74% | -33.6 | behind | 30 Jun 2027 | Jul 2029 – Sept 2029 | dubairealestateiq.com |
| Verve City Walk Meraas · Al Wasl | 17.7% 4 Nov 2026 | 51% | -33.6 | behind | 15 Sept 2028 | Dec 2035 – Sept 2037 | dubairealestateiq.com |
| Blossom 76 by Tranquil Tranquil Infra · Jumeirah Village Circle | 40% 14 Aug 2026 | 74% | -33.6 | behind | 26 Mar 2027 | Mar 2029 | dubairealestateiq.com |
| Belgravia Gardens Ellington Properties · Wadi Al Safa 2 | 3.1% 4 Jun 2026 | 37% | -33.5 | behind | 30 Sept 2028 | under 10% built: too early to project | dubairealestateiq.com |
| W Residences at Dubai Harbour Arada · Dubai Marina | 4% 13 Oct 2026 | 38% | -33.5 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Arthouse Residences Tower A by Aviaan Aviaan · Nad Al Shiba First | 0% 22 Jun 2026 | 34% | -33.5 | behind | 30 Nov 2027 | under 10% built: too early to project | dubairealestateiq.com |
| The Valley - Rivera Emaar Properties · Al Yufrah 1 | 3.9% 6 May 2026 | 37% | -33.4 | behind | 30 Nov 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Marina Cove Emaar Properties · Dubai Marina | 5.7% 1 Oct 2026 | 39% | -33.4 | behind | 30 Sept 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Waada - Raiha BT Properties · Madinat Al Mataar | 7% 20 Oct 2026 | 40% | -33.4 | behind | 31 Oct 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Saddlewood Park MAK Developers · Nad Al Shiba First | 12.5% 24 Aug 2026 | 46% | -33.4 | behind | 30 Sept 2027 | Mar 2033 | dubairealestateiq.com |
| Casa Aura Residence A G N Skyline · Madinat Al Mataar | 6.3% 4 May 2026 | 40% | -33.4 | behind | 12 Sept 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Sparklz by Danube Danube Properties · Al Furjan | 7.8% 25 Aug 2026 | 41% | -33.3 | behind | 31 May 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Jad 288 Jad Global · Al Satwa | 1.9% 27 Jul 2026 | 35% | -33.3 | behind | 31 Dec 2027 | under 10% built: too early to project | dubairealestateiq.com |
| Rijas Suites Dusit Rijas Properties · Majan | 3.3% 29 Jun 2026 | 37% | -33.3 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Samana Imperial Garden Samana Developers · Arjan | 4.2% 23 Oct 2026 | 38% | -33.2 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Azizi Wares Azizi Developments · Jabal Ali Industrial Second | 2% 16 Nov 2026 | 35% | -33.2 | behind | 4 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Marquis One Marquis · Arjan | 0.3% 19 Oct 2026 | 34% | -33.2 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| 997 Residences by Reef Luxury Development Reef Luxury Development · Palm Deira | 4.9% 27 Aug 2026 | 38% | -33.2 | behind | 30 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Wadi Hills by HRE Wadi Hills City Real Estate Development L.L.C · Dubai Land Residence Complex | 7.7% 14 Sept 2026 | 41% | -33.2 | behind | 31 Jan 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Derby Heights A M I S · Majan | 10.1% 2 Sept 2026 | 43% | -33.2 | behind | 31 Oct 2027 | Jul 2034 | dubairealestateiq.com |
| Mar Casa Deyaar Development PJSC · Dubai Maritime City | 66.8% 29 Oct 2026 | 100% | -33 | behind | 31 Oct 2026 | Aug 2027 – Aug 2028 | dubairealestateiq.com |
| Olaia Residences Gulf House · Palm Jumeirah | 14.3% 21 Jul 2026 | 47% | -33 | behind | 31 Dec 2027 | May 2034 | dubairealestateiq.com |
| Maison Margiela Residences Alta Real Estate Development L.L.C · Palm Jumeirah | 6.4% 5 Oct 2026 | 39% | -32.9 | behind | 27 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Lacina Majid Al Futtaim · City of Arabia | 30.4% 3 Nov 2026 | 63% | -32.9 | behind | 30 Dec 2027 | May 2031 | dubairealestateiq.com |
| Rome 3 by Sd SAMANA Developers · Majan | 10.2% 15 Oct 2026 | 43% | -32.8 | behind | 30 Jun 2028 | Jun 2035 – Feb 2038 | dubairealestateiq.com |
| Samana Hills South Samana Developers · Dubai South / Dubai Industrial City | 12.1% 28 Sept 2026 | 45% | -32.7 | behind | 15 May 2028 | Nov 2035 – May 2036 | dubairealestateiq.com |
| Avenew888-Loom Avenew · Madinat Al Mataar | 1.6% 13 Oct 2026 | 34% | -32.7 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Bond Enclave Pearlshire · Arjan | 20% 20 Jul 2026 | 53% | -32.7 | behind | 30 Nov 2027 | Aug 2032 | dubairealestateiq.com |
| Lume Residences S&S · Jumeirah Village Circle | 21.7% 19 Aug 2026 | 54% | -32.6 | behind | 30 Sept 2027 | May 2031 | dubairealestateiq.com |
| Blue Marina Residence by Shakirov Developments Shakirov · Palm Deira | 13.4% 28 Sept 2026 | 46% | -32.6 | behind | 31 Oct 2027 | Sept 2032 | dubairealestateiq.com |
| Empire Lakeviews Empire · Wadi Al Safa 2 | 2.1% 23 Mar 2026 | 35% | -32.4 | behind | 24 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Repose Residence Saion · Jabal Ali First | 37.5% 15 Oct 2026 | 70% | -32.3 | behind | 31 Mar 2027 | Jul 2028 | dubairealestateiq.com |
| Taraf 3 Residence Taraf Properties · Jumeirah Village Circle | 6.9% 23 Oct 2026 | 39% | -32.2 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Blossom 40 Tranquil Infra · Majan | 0% 10 Sept 2026 | 32% | -32 | behind | 31 Mar 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Maybach Six Binghatti Developers · Nad Al Shiba First | 17.5% 3 Nov 2026 | 49% | -31.9 | behind | 31 Aug 2027 | Aug 2030 | dubairealestateiq.com |
| Auresta Tower Tiger Properties · Jumeirah Village Circle | 4.4% 8 Oct 2026 | 36% | -31.9 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Samana Boulevard Heights Samana Developers · Dubailand Residence Complex | 6.6% 5 Nov 2026 | 39% | -31.8 | behind | 31 Dec 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Jumeirah Asora Bay Dubai Holding Real Estate · La Mer | 4.4% 12 Aug 2026 | 36% | -31.8 | behind | 31 Mar 2029 | under 10% built: too early to project | dubairealestateiq.com |
| Taormina Village 1 Reportage Properties · Majan | 20.4% 3 Jun 2026 | 52% | -31.8 | behind | 20 Dec 2027 | Jan 2033 | dubairealestateiq.com |
| Capria East Majid Al Futtaim · City of Arabia | 7.1% 30 Oct 2026 | 39% | -31.8 | behind | 15 May 2029 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Avenue SAMANA Developers · Dubai Land Residence Complex (DLRC) | 31.8% 1 Oct 2026 | 64% | -31.7 | behind | 31 Dec 2027 | May 2031 | dubairealestateiq.com |
| One.B Tower Wasl · Business Bay | 10.1% 8 Oct 2026 | 42% | -31.7 | behind | 31 Dec 2028 | Jan 2041 – Nov 2044 | dubairealestateiq.com |
| Beachfront Gates 2 Dubai South Properties · Madinat Al Mataar | 61.4% 12 Nov 2026 | 93% | -31.7 | behind | 30 Dec 2026 | Dec 2027 | dubairealestateiq.com |
| Elle Residences Anax · Palm Deira | 0% 7 May 2026 | 32% | -31.7 | behind | 1 Sept 2027 | under 10% built: too early to project | dubairealestateiq.com |
| SAMANA Park Meadows SAMANA Developers · Dubai Land Residence Complex (DLRC) | 38% 1 Oct 2026 | 70% | -31.6 | behind | 31 Aug 2027 | Mar 2030 | dubairealestateiq.com |
| Maybach Ultimate Luxury Binghatti Developers · Nad Al Shiba First | 17.7% 3 Nov 2026 | 49% | -31.6 | behind | 31 Aug 2027 | Jul 2030 | dubairealestateiq.com |
| South Square Dubai South Properties · Madinat Al Mataar | 2.6% 17 Jun 2026 | 34% | -31.5 | behind | 30 Jun 2028 | under 10% built: too early to project | dubairealestateiq.com |
| Capria West Majid Al Futtaim · City of Arabia | 8.4% 30 Oct 2026 | 40% | -31.5 | behind | 8 May 2029 | under 10% built: too early to project | dubairealestateiq.com |
Method
Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.
Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.
Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.
Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.
Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.