Aykon City 3, Dubai: a completion date that moved from 2022 to 2027
A documented case, told only with facts from the Dubai Land Department project register and published pages, each with its source and the date we read it. No verdict on the developer: what the record shows, and what a buyer can check.
Reviewed on .
The project
Aykon City 3 (marketed as Safa Two de GRISOGONO) is a DAMAC project in Business Bay, Dubai. It is registered with the Dubai Land Department (DLD) as project 2200, registered on , with construction start and registered developer Damac Canal One Property Development L.L.C (DLD developer 1119). About 1,300 units in 4 buildings. Escrow account bank listed on the register: Emirates NBD Bank. dubairealestateiq.com
The first date on record
Our research record of holds a registered completion date of , taken from earlier DLD data published on binayah.com. That page, read again on , still shows "Target handover Q3 2022" and a progress figure of 3.08%. binayah.com
What the register says now
On the DLD project register, as republished by dubairealestateiq.com, listed the project as Active, with a completion date of and 38.27% built at the DLD inspection of . The date moved by 63 months from the first date on record. An agency page carrying the developer's figures gives handover Q4 2027. dubairealestateiq.com a1properties.ae
The DLD's own Project Status Enquiry service shows a captcha, so our software cannot read it; the figures above are the register's as republished, and anyone can check them by hand on the DLD service. dubailand.gov.ae
Every DLD inspection on the register
| Inspection date | Built (DLD) | Change since the previous inspection |
|---|---|---|
| 38.27 % | +6.92 | |
| 31.35 % | +5.00 | |
| 26.35 % | +2.99 | |
| 23.36 % | +5.27 | |
| 18.09 % | +8.39 | |
| 9.70 % | +3.14 | |
| 6.56 % | +3.48 | |
| 3.08 % | +0.38 | |
| 2.70 % | +1.41 | |
| 1.29 % | +0.27 | |
| 1.02 % |
The arithmetic, not a forecast
From the inspection of to that of (50 months), the built share rose by 37.25 points: 0.74 points a month on average. Over the last two inspections ( to ) it rose by 6.92 points in 7 months. To reach 100% by , the remaining 61.73 points would need 4.5 points a month. This is arithmetic on the register's own figures. Building work is not linear, and it says nothing certain about the date the project will be finished.
From space
Our monthly Sentinel-2 series for the site recorded visible change (15.1% of the measured circle differing from its first clear month, reading of ). Satellite pixels are 10 m: they show slabs and roofs, not floors. kolaboro.com
The developer's record
TradeArabia reported on 9 Jul 2026 that DAMAC, founded in 2002, had delivered 50,000 units, and announced the handover of 8,800 residential units across Dubai. The full record of this developer's projects that we track is on its page. tradearabia.com DAMAC Properties
What a buyer in this project can check
- The completion date written in your sale contract (SPA) and what the contract says happens if it passes.
- That every payment goes to the escrow account the register lists for the project, and that the account in your contract is that one.
- That your unit is registered in your name on the DLD interim register (Oqood).
- The latest inspection percentage, by hand, on the DLD Project Status Enquiry service.
Developer's reply
DAMAC has not replied to this case yet. A reply with documents is published next to the facts it answers, after a person has read it.
The full project page, with every fact and source · Data of this case (JSON)
Sources
- dubairealestateiq.com DLD project register as republished by dubairealestateiq.com (project 2200, inspections, escrow bank, completion date) (read )
- binayah.com binayah.com construction update page ("Target handover Q3 2022", 3.08%) (read )
- a1properties.ae A1 Properties agency page (handover Q4 2027, permit 1982041975) (read )
- tradearabia.com TradeArabia, 9 Jul 2026 (50,000 units delivered since 2002; 8,800 units handed over) (read )
- dubailand.gov.ae DLD Project Status Enquiry (captcha; probed by our checker on 13 Nov 2026) (read )
- kolaboro.com Kolaboro Sentinel-2 construction series