Kolaboro / Projects / Philippines
Haraya Residences: reviews and facts
What is published about Haraya Residences in Bridgetowne Destination Estate, Pasig City, Metro Manila, Philippines, what official registers and other sources say, and what changed over time. Facts only, each with its source.
- Location
- Bridgetowne Destination Estate, Pasig City, Metro Manila, Philippines
- Stage
- under construction shangpropertiesinternationalsales.com
- Handover on record
- September 2028 shangpropertiesinternationalsales.com
- Permit or licence number
- DHSUD Provisional License to Sell No. 2537 (issued 3 Nov 2022) per website; LS No. 489 per technical brochure harayaresidences.com
- Deposit protection
- not researched yet
- Page we read
- shangpropertiesinternationalsales.com shangpropertiesinternationalsales.com
- Last checked
- 5 Nov 2026
- Open data record
- PHL-007
In short
- Haraya Residences is listed as under construction in Bridgetowne Destination Estate, Pasig City, Metro Manila, Philippines, by Shang Robinsons Properties, Inc.. shangpropertiesinternationalsales.com
- The handover date on record is September 2028. shangpropertiesinternationalsales.com
- A permit or licence number is published. harayaresidences.com
- Of 11 developer claims we checked, 6 are confirmed by a register or an independent source, 3 are not yet verified and 2 are contradicted by another source. Open data record
What is promised
As published by the developer or on listing pages, in the wording of the source.
- Units: 895 shangpropertiesinternationalsales.com
- Unit sizes: 60 - 555 m² shangpropertiesinternationalsales.com
- Unit types: 1BR, 2BR, 3BR, penthouse 4BR shangpropertiesinternationalsales.com
- Ownership: Condominium unit within the 40% foreign-ownership cap shangpropertiesinternationalsales.com
- Brand or operator: Shang Properties shangpropertiesinternationalsales.com
- Permit authority: DHSUD (License to Sell, advertising approval) shangpropertiesinternationalsales.com
- Handover promised: Q3 2028 shangpropertiesinternationalsales.com
- developer: DHSUD Provisional LTS No. 2537, date issued 3 Nov 2022, DHSUD NCR AA-2026/06-5155 (website footer and LTS page) harayaresidences.com
- developer: completion South Tower 31 Jul 2028, North Tower 30 Sep 2028 harayaresidences.com
- developer: 21 unit floor plan PDFs (North and South Towers) harayaresidences.com
- developer: technical brochure Jan 2026 with unit sizes, unit mix, LS No. 489 harayaresidences.com
- developer: quarterly construction updates Q1, Q2, Q3 2026 harayaresidences.com
- developer: FAQ with 533 + 362 units, 57 and 45 residential floors, 702 parking harayaresidences.com
Delivery and delay record
Every dated promise we found, how it changed and whether the date has passed. Status rules: promise tracker.
- Handover or completion: September 2028 date still ahead
our research record of 31 Oct 2026 shangpropertiesinternationalsales.com
Permits and licences
- Number published: DHSUD Provisional License to Sell No. 2537 (issued 3 Nov 2022) per website; LS No. 489 per technical brochure. harayaresidences.com
- Website footer and /license-to-sell page: 'DHSUD Provisional License to Sell No. 2537, Date Issued: 3 November 2022'; technical brochure: 'DHSUD LS No.: 489'; DHSUD list (lumingon mirror) shows PLS 489 (Nov 2022) and LS 0002524 (Jun 2026), no entry for 2537 found harayaresidences.com
Live check in the official registers
Queries the official registers we can reach for this country now and shows what each returns. Each answer is hashed (SHA-256); nothing is invented, a register with no data says so.
The six buyer checks
Public means the information is published. The level says who confirms it. Method: how we score.
| Check | Public | Who confirms it | What we found |
|---|---|---|---|
| Permit or licence number | yes | confirmed in an official register | Website footer and /license-to-sell page: 'DHSUD Provisional License to Sell No. 2537, Date Issued: 3 November 2022'; technical brochure: 'DHSUD LS No.: 489'; DHSUD list (lumingon mirror) shows PLS 489 (Nov 2022) and LS 0002524 (Jun 2026), no entry for 2537 found harayaresidences.com |
| Deposit protection | no | not published | |
| Construction progress | yes | confirmed by an independent source | Developer construction updates Q1-Q3 2026; Q3 2026: formworks Level 50 South Tower, Level 35 North Tower; BusinessWorld (11 May 2026) reports 26th and 16th floors reached harayaresidences.com |
| Floor or site plans | yes | stated only by the developer | Floor plans page with downloadable PDFs per unit type; technical brochure with typical floor plan harayaresidences.com |
| Developer track record | yes | stated only by the developer | Brochure lists completed Shang Properties projects (developer statement only) harayaresidences.com |
| No guaranteed returns | yes | stated only by the developer | No rental guarantee or yield language found harayaresidences.com |
Developer claims we tested
| Claim (source wording) | Result | Checked against | Source |
|---|---|---|---|
| Project holds DHSUD provisional License to Sell (Nov 2022) | verified | registry | lumingon.com |
| LTS number is 2537 (website) | contradicted | registry | lumingon.com |
| Further LTS LS 0002524 issued Jun 2026 to Shang Robinsons Properties | verified | registry | lumingon.com |
| Developer is a JV of Shang Properties and Robinsons Land | verified | independent | bworldonline.com |
| Construction reached 26th floor South and 16th floor North (Apr 2026) | verified | independent | bworldonline.com |
| Formworks at Level 50 South, Level 35 North (Q3 2026) | not verified yet | harayaresidences.com | |
| Completion South Jul 2028, North Sep 2028 | verified | independent | bworldonline.com |
| South Tower 558 units over 57 floors | verified | independent | bworldonline.com |
| South Tower unit count 533 (FAQ) vs 558 (brochure) | contradicted | independent | harayaresidences.com |
| Shang delivered Shang Grand Tower, One Shangri-La Place and others | not verified yet | harayaresidences.com | |
| Price | not verified yet | shangpropertiesinternationalsales.com |
What changed, with dates
- No dated change recorded yet.
- Fingerprint of the developer page text on 5 Nov 2026: SHA-256
6dcbcba2f5f1c463.... Anyone can check it on kolaboro.com/verify. kolaboro.com/verify
Public reports
What public sources report, with the link. We list reports; we do not judge the developer.
- No reports of disputes, regulator action, stoppages or financial difficulty found in the sources we read.
About the developer
- Head office: Metro Manila, Philippines shangpropertiesinternationalsales.com
- Listed or audited: Parents Shang Properties, Inc. and Robinsons Land Corporation are PSE-listed shangpropertiesinternationalsales.com
- Brochure lists completed Shang Properties projects (developer statement only) shangpropertiesinternationalsales.com
Similar projects
- Mandtra Residences Tower 3 (Phase 2) Philippines · under construction
- Fortis Residences Philippines · under construction
- Savoy Hotel Palawan (condotel) Philippines · under construction
- Mandani Bay Quay Philippines · under construction
- CostaVida Residential Resort Philippines · off-plan
Market context: Philippines
- We track 14 projects in Philippines. 79% publish a permit or licence number and 0% state deposit protection. kolaboro.com/m
Buyer reviews
There are no verified buyer reviews of Haraya Residences yet. We publish a review only from a buyer who proves the purchase (fingerprint of the contract or receipt, signed with a passkey) and only after a moderator has read it.
Reviews waiting for moderation are not shown.
Right of reply
Are you the developer? Send documents and we add your reply to this page. Found a wrong fact? Tell us and we correct it with a dated note.
Reply as the developer Report a correction Questions to ask the developer
Before you pay
Paste the project link for a free live check of what official registers say. For a full desk review and a site visit by a local agent, order the pre-purchase check.
Questions buyers ask
Is Haraya Residences legit?
Kolaboro does not label projects or developers. What the public record shows: A permit or licence number is published. Of 11 developer claims we checked, 6 are confirmed by a register or an independent source, 3 are not yet verified and 2 are contradicted by another source. The handover date on record is September 2028. No reports of disputes, regulator action, stoppages or financial difficulty found in the sources we read. Check the sources on this page and ask the developer for documents before paying.
When will Haraya Residences be delivered?
The handover date on record is September 2028.
Who is the developer of Haraya Residences?
Shang Robinsons Properties, Inc., according to the sources listed on this page.
Does Haraya Residences have a permit or licence?
A permit or licence is confirmed in an official register (see Permits and licences).
Are there reviews of Haraya Residences?
There are no verified buyer reviews yet. Buyers who prove their purchase can submit one; it is published after moderation.
Sources
Every fact on this page links to its source. Pages we read are fingerprinted and kept by date.
- shangpropertiesinternationalsales.com https://shangpropertiesinternationalsales.com/project/haraya-residences/
- harayaresidences.com https://harayaresidences.com/
- buildmartasean.com http://www.buildmartasean.com/article/news/haraya-residences-in-bridgetowne-estate-pasig-c...
- bworldonline.com https://bworldonline.com/corporate/2026/05/11/748615/shang-robinsons-venture-advances-hara...
- harayaresidences.com https://harayaresidences.com/app/uploads/2026/01/Haraya-Residences-Technical-Brochure-Sout...
- harayaresidences.com https://harayaresidences.com/brochures-faqs/
- harayaresidences.com https://harayaresidences.com/floor-plans/
- harayaresidences.com https://harayaresidences.com/haraya-residences-construction-update-q3-2026/
- harayaresidences.com https://harayaresidences.com/license-to-sell/
- lumingon.com https://lumingon.com/license-to-sell/haraya-residences--4e1dcf099ca04d03bdb649c04675c47f
- lumingon.com https://lumingon.com/license-to-sell/haraya-residences--d90dfd66688543e28a5d5346f794c9ff
Last checked 5 Nov 2026. How we collect data: data policy. Facts quoted from sources are shown in the language of the source.