In Colombia, Kolaboro has reviewed 8 off-plan projects in 3 markets (4 off-plan, 4 under construction). On average 2.9 of 6 buyer checks are public and 0.5 are confirmed by an official register or independent source.
2 projects are past the first handover date we have on record; 1 is past the date currently advertised. Data of 5 November 2026.
Markets in Colombia#
Off-plan projects tracked in Colombia#
Sorted by the number of buyer checks the developer makes public. Facts as advertised, checked against registers where we could; "not published" means we found no public source.
| Project | Where | Stage | Handover year advertised | Checks public | Confirmed by register or independent source | Past first handover date on record |
|---|---|---|---|---|---|---|
| Morros Vita CAR-001 | Cartagena | under construction | 2028 | 4/6 | 3/6 | not past |
| Amalfi Tower COL-001 | Colombia | under construction | 2028 | 4/6 | 0/6 | not past |
| Ika Mare COL-003 | Colombia | off-plan | 2029 | 3/6 | 0/6 | not past |
| Reserva Natural San José Natura MED-001 | Medellín | under construction | 2023 | 3/6 | 0/6 | 35 months |
| The Gray Zone MED-002 | Medellín | off-plan | not published | 3/6 | 0/6 | no date |
| The Anti Galerie Hotel COL-002 | Colombia | under construction | 2026 | 2/6 | 0/6 | 1 months |
| Veranova Park (Ciudad Veranova phase 1) MED-003 | Medellín | off-plan | 2028 | 2/6 | 1/6 | not past |
| Proyecto Alejandria MED-004 | Medellín | off-plan | not published | 2/6 | 0/6 | no date |
Furthest past the first handover date#
- Reserva Natural San José Natura (Medellín): first handover on record December 2023, 35 months ago
- The Anti Galerie Hotel (Colombia): first handover on record October 2026, 1 months ago; date moved 2 months in total
Source: /data/on-time.json (as of 2026-11). All markets
Delivery-delay index#
| Market | Tracked | With a date | Past first date | Share past first date | Median months late |
|---|---|---|---|---|---|
| Colombia | 3 | 3 | 1 | null% | too few |
| Medellín | 4 | 2 | 1 | null% | too few |
| Cartagena | 1 | 1 | 0 | null% | too few |
Source: delivery-delay index, /data/delay-index.json.
Dated promises: kept, broken, moved#
| Market | Promises | Kept | Broken | Moved | Pending |
|---|---|---|---|---|---|
| Medellín | 3 | 0 | 2 | 0 | 1 |
| Colombia | 3 | 0 | 1 | 0 | 2 |
| Cartagena | 1 | 0 | 0 | 1 | 0 |
Each promise is an exact quote from the developer page or research record: promise tracker, /data/promises.json.
Official registers for Colombia#
We have not yet documented an official online register for Colombia. Ask the developer for the permit number and the document that protects your deposit, then check them with the issuing authority; see the registers we cover.
Questions and answers#
How many off-plan projects does Kolaboro track in Colombia?
8 projects in 3 markets (Medellín, Colombia, Cartagena), data of 5 November 2026.
How many off-plan projects in Colombia publish a permit or licence number?
0 of 8 (0%). 1 are confirmed in an official register or by an independent source.
How many off-plan projects in Colombia state deposit protection such as escrow?
7 of 8 (88%).
Are off-plan projects in Colombia delivered late?
2 of 8 tracked projects are past the first handover date on record, the furthest by 35 months. 1 are past the date they currently advertise.