Kolaboro / Projects / Zanzibar
ANGA Zanzibar: reviews and facts
What is published about ANGA Zanzibar in Paje Main Road, South East Coast, Zanzibar, Tanzania, what official registers and other sources say, and what changed over time. Facts only, each with its source.
- Developer
- LZDM Ltd angazanzibar.com
- Location
- Paje Main Road, South East Coast, Zanzibar, Tanzania
- Stage
- under construction · active angazanzibar.com
- Handover on record
- Q3 2027 angazanzibar.com
- Permit or licence number
- not published
- Deposit protection
- not researched yet
- Page we read
- angazanzibar.com angazanzibar.com
- Last checked
- 5 Nov 2026
- Open data record
- ZNZ-005
In short
- ANGA Zanzibar is listed as under construction in Paje Main Road, South East Coast, Zanzibar, Tanzania, by LZDM Ltd. angazanzibar.com
- The handover date on record is Q3 2027. angazanzibar.com
- No permit or licence number is published in the sources we read. angazanzibar.com
- Of 12 developer claims we checked, 1 are confirmed by a register or an independent source, 8 are not yet verified and 3 are contradicted by another source. Open data record
- The handover date moved 1 times in our records, by 3 months in total. promise tracker
What is promised
As published by the developer or on listing pages, in the wording of the source.
- Price from: USD 143,000 angazanzibar.com
- Units: 82 angazanzibar.com
- Unit types: 1BR, 2BR duplex, 3BR, 4BR duplex angazanzibar.com
- Payment plan: 8/17/30/35/10 milestone plan angazanzibar.com
- Ownership: 99-year renewable leasehold unit title under the Condominium Act via a ZIPA-approved project angazanzibar.com
- Permit authority: Zanzibar Investment Promotion Authority (ZIPA), Condominium Board, Department of Urban and Rural Planning angazanzibar.com
- Deposit: 25% angazanzibar.com
- Construction start: November 2025 angazanzibar.com
- Handover promised: Q3 2027 angazanzibar.com
- Original handover date: Q2 2027 angazanzibar.com
- developer: 1BR from USD 143,000; '14-16% annual ROI' angazanzibar.com
- developer: floor-by-floor apartment and duplex plans angazanzibar.com
- developer: monthly construction log with photos since July 2025, live camera angazanzibar.com
- developer: payment plan 8/17/30/35/10 tied to structural milestones angazanzibar.com
- developer: 82 apartments registered under the Condominium Board, completion Q3 2027 angazanzibar.com
- developer: contractor Boge Investment Co. (ZCRB licensed), lawyers Lawbridge angazanzibar.com
- news: The Citizen launch article Sep 2025 (72 duplexes, from USD 189,750, Q2 2027) angazanzibar.com
Delivery and delay record
Every dated promise we found, how it changed and whether the date has passed. Status rules: promise tracker.
- Handover or completion: Q3 2027 date moved later · moved 1 times, 3 months in total
our research record of 1 Nov 2026 · Earlier dates on record: Q2 2027 (1 Nov 2026) angazanzibar.com - Delay stated in the sources we read: 3 months. angazanzibar.com
Permits and licences
- No permit or licence number is published in the sources we read.
- FAQ says LZDM is registered with ZIPA as an approved project developer and that the Condominium Board approved the scheme; no ZIPA certificate, building permit or condominium registration number published angazanzibar.com
Live check in the official registers
Queries the official registers we can reach for this country now and shows what each returns. Each answer is hashed (SHA-256); nothing is invented, a register with no data says so.
The six buyer checks
Public means the information is published. The level says who confirms it. Method: how we score.
| Check | Public | Who confirms it | What we found |
|---|---|---|---|
| Permit or licence number | no | stated only by the developer | FAQ says LZDM is registered with ZIPA as an approved project developer and that the Condominium Board approved the scheme; no ZIPA certificate, building permit or condominium registration number published angazanzibar.com |
| Deposit protection | no | not published | No escrow or bank guarantee; payments go to developer by milestone; only the KYC refund of the reservation deposit is stated angazanzibar.com |
| Construction progress | yes | stated only by the developer | Monthly construction log and photo gallery (Sep 2026 latest gallery: concrete casting); log text also lists future months (Nov 2026 to Mar 2027) as completed stages, so it mixes plan and record angazanzibar.com |
| Floor or site plans | yes | stated only by the developer | Apartments page shows floor and duplex plans per level angazanzibar.com |
| Developer track record | no | not published | No completed projects by LZDM Ltd named; architect's past work (Bamboo Hotel Jambiani) cited by The Citizen angazanzibar.com |
| No guaranteed returns | yes | not published | Homepage advertises '14-16% annual ROI'; not called guaranteed angazanzibar.com |
Developer claims we tested
| Claim (source wording) | Result | Checked against | Source |
|---|---|---|---|
| Construction of main building began (Nov 2025) | not verified yet | angazanzibar.com | |
| Completion Q3 2027 | contradicted | independent | thecitizen.co.tz |
| 82 apartments | contradicted | independent | thecitizen.co.tz |
| Architect is Lucas Oteyza | verified | independent | thecitizen.co.tz |
| Developer registered with ZIPA as approved project | not verified yet | angazanzibar.com | |
| Scheme approved by the Condominium Board | not verified yet | angazanzibar.com | |
| Construction log stages Nov 2026 to Mar 2027 completed | contradicted | angazanzibar.com | |
| Contractor Boge Investment Co. licensed by ZCRB | not verified yet | angazanzibar.com | |
| 14-16% annual ROI | not verified yet | angazanzibar.com | |
| Prices from USD 143,000 (1BR) | not verified yet | angazanzibar.com | |
| Foreigners get 99-year leasehold unit title and residence permit above USD 100,000 | not verified yet | angazanzibar.com | |
| Buyer payments protected by escrow | not verified yet | angazanzibar.com |
What changed, with dates
- No dated change recorded yet.
- Fingerprint of the developer page text on 5 Nov 2026: SHA-256
6e89f7fea531ce94.... Anyone can check it on kolaboro.com/verify. kolaboro.com/verify
Public reports
What public sources report, with the link. We list reports; we do not judge the developer.
- No reports of disputes, regulator action, stoppages or financial difficulty found in the sources we read.
About the developer
- Head office: Zanzibar, Tanzania angazanzibar.com
- Legal entity: LZDM Ltd angazanzibar.com
- No completed projects by LZDM Ltd named; architect's past work (Bamboo Hotel Jambiani) cited by The Citizen angazanzibar.com
Similar projects
- Infinity Hills (Phase One) Zanzibar · off-plan
- The Soul Fumba Zanzibar · under construction
- Chukwani Shores Zanzibar · under construction
- AZURE Michamvi (The House Residence Azure Zanzibar) Zanzibar · under construction
- Shivo Towers Zanzibar · off-plan
Market context: Zanzibar
- We track 6 projects in Zanzibar. 0% publish a permit or licence number and 0% state deposit protection. kolaboro.com/m
Buyer reviews
There are no verified buyer reviews of ANGA Zanzibar yet. We publish a review only from a buyer who proves the purchase (fingerprint of the contract or receipt, signed with a passkey) and only after a moderator has read it.
Reviews waiting for moderation are not shown.
Right of reply
Are you the developer? Send documents and we add your reply to this page. Found a wrong fact? Tell us and we correct it with a dated note.
Reply as the developer Report a correction Questions to ask the developer
Before you pay
Paste the project link for a free live check of what official registers say. For a full desk review and a site visit by a local agent, order the pre-purchase check.
Questions buyers ask
Is ANGA Zanzibar legit?
Kolaboro does not label projects or developers. What the public record shows: No permit or licence number is published in the sources we read. Of 12 developer claims we checked, 1 are confirmed by a register or an independent source, 8 are not yet verified and 3 are contradicted by another source. The handover date on record is Q3 2027. No reports of disputes, regulator action, stoppages or financial difficulty found in the sources we read. Check the sources on this page and ask the developer for documents before paying.
When will ANGA Zanzibar be delivered?
The handover date on record is Q3 2027. The handover date moved 1 times in our records, by 3 months in total.
Who is the developer of ANGA Zanzibar?
LZDM Ltd, according to the sources listed on this page.
Does ANGA Zanzibar have a permit or licence?
No permit or licence number is published in the sources we read.
Are there reviews of ANGA Zanzibar?
There are no verified buyer reviews yet. Buyers who prove their purchase can submit one; it is published after moderation.
Sources
Every fact on this page links to its source. Pages we read are fingerprinted and kept by date.
- angazanzibar.com https://angazanzibar.com/
- angazanzibar.com https://angazanzibar.com/faqs/
- angazanzibar.com https://angazanzibar.com/apartments/
- angazanzibar.com https://angazanzibar.com/construction-log/
- thecitizen.co.tz https://www.thecitizen.co.tz/tanzania/zanzibar/anga-zanzibar-new-flagship-residential-inve...
Last checked 5 Nov 2026. How we collect data: data policy. Facts quoted from sources are shown in the language of the source.