Whether buying off-plan in Turkey is safe depends on the project, and the public record differs a lot between projects. Of the 27 projects we track, 33% publish a permit or licence number, 19% state deposit protection and 6 are past the first handover date on record.
We found 42 developer claims contradicted by another source out of 272 tested, and public reports of problems for 3 projects. This page reports facts; it is not a rating of any company.
Delivery record#
6 of 27 projects are past the first handover date on record (median 11 months). 8 projects have a first handover date more than six months in the past, the group used for the on-time odds on the delay index.
Dated promises (handover, construction start, permits): 23 tracked, 1 kept, 1 broken, 5 moved to a later date, 16 still ahead. How promises are tracked.
What developers make public#
| Check | Public | Confirmed by register or independent source |
|---|---|---|
| Permit or licence number | 33% (9) | 12 |
| Deposit protection | 19% (5) | 1 |
| Construction progress | 81% (22) | 12 |
| Site or floor plans | 52% (14) | 0 |
| Developer track record | 81% (22) | 6 |
| No guaranteed-return language | 100% (27) | 0 |
Public reports of problems#
Our research agent found public reports of problems (for example a court case, a regulator notice or press coverage) for 3 of 27 projects. Each project page names the report and links its source; we do not summarise them here.
What protects a buyer#
The protections that exist on paper only help if the project uses them: a permit you can look up, payments into an escrow or protected account in the project name, and payments tied to construction milestones you can verify. How to check a project in Turkey.
Questions and answers#
Is it safe to buy off-plan property in Turkey?
It depends on the project. Of 27 projects tracked by Kolaboro in Turkey, 33% publish a permit number, 19% state deposit protection and 6 are past the first handover date on record (data of 5 November 2026).
How often are off-plan handovers in Turkey late?
6 of 27 tracked projects are past the first handover date on record, median 11 months.
How many developer claims in Turkey turned out to be contradicted?
42 of 272 tested claims (15%) were contradicted by a register or independent source.
Are you the developer, or did we get something wrong? Send documents and we add your reply or correct the record: right of reply · corrections. Every figure here is computed from the open dataset (/data/bali-cases.json, CC BY 4.0) and changes when the data changes.