Shipping daily
Nov 1DATAAll 646 projects re-verified: 6,419 developer claims tested against registers, courts and pressNov 1DATAMalaysia TEDUH and Philippines DHSUD licence checks: expired licences and approved delays foundNov 1DATAThailand ONEP register: 2 condos found selling before environmental approvalNov 1DATAMexico PROFECO contract register checks: one sales registration belonged to a laundryNov 1DATAAbu Dhabi ADREC inspections and RAK RERA permit list added: % built straight from the regulatorNov 1SHIPPEDNew stage filter: completed but still sellingNov 1SHIPPEDPublic database page: verification levels, disclosure distribution, every marketNov 1DATA+212 projects in one day, round 3: USA, Caribbean, Gulf, Africa, Japan, AustraliaNov 1SHIPPEDStage on every case: off-plan or under constructionOct 31SHIPPEDVerification level per check on every case card: registry, independent, developer, contradicted
Changelog →

Kolaboro / Countries / Portugal / Is it safe?

Is it safe to buy off-plan in Portugal?

What the delivery record, dated promises and public documents of 25 tracked projects show.

Whether buying off-plan in Portugal is safe depends on the project, and the public record differs a lot between projects. Of the 25 projects we track, 4% publish a permit or licence number, 0% state deposit protection and 2 are past the first handover date on record.

We found 25 developer claims contradicted by another source out of 218 tested. This page reports facts; it is not a rating of any company.

4%publish a permit number
0%state deposit protection
2past first handover date
24dated promises tracked
3promises broken
11%of tested claims contradicted

Delivery record#

2 of 25 projects are past the first handover date on record (median 22 months). 10 projects have a first handover date more than six months in the past, the group used for the on-time odds on the delay index.

Dated promises (handover, construction start, permits): 24 tracked, 0 kept, 3 broken, 4 moved to a later date, 15 still ahead. How promises are tracked.

What developers make public#

CheckPublicConfirmed by register or independent source
Permit or licence number4% (1)2
Deposit protection0% (0)0
Construction progress20% (5)8
Site or floor plans56% (14)0
Developer track record60% (15)8
No guaranteed-return language88% (22)1

What protects a buyer#

The protections that exist on paper only help if the project uses them: a permit you can look up, payments into an escrow or protected account in the project name, and payments tied to construction milestones you can verify. 1 rules of Portugal law, quoted from the official text. How to check a project in Portugal.

Questions and answers#

Is it safe to buy off-plan property in Portugal?

It depends on the project. Of 25 projects tracked by Kolaboro in Portugal, 4% publish a permit number, 0% state deposit protection and 2 are past the first handover date on record (data of 5 November 2026).

How often are off-plan handovers in Portugal late?

2 of 25 tracked projects are past the first handover date on record, median 22 months.

How many developer claims in Portugal turned out to be contradicted?

25 of 218 tested claims (11%) were contradicted by a register or independent source.

Are you the developer, or did we get something wrong? Send documents and we add your reply or correct the record: right of reply · corrections. Every figure here is computed from the open dataset (/data/bali-cases.json, CC BY 4.0) and changes when the data changes.

Protect my purchase