Construction pace against the registered date

For Dubai projects with DLD inspection readings: % built against the share of time elapsed to the completion date on the register, and the completion range the observed pace points to. A projection, not a promise.

Updated 23 Nov 2026

A projection from the pace on the register, not a promise, and not a finding about the developer.

860projects compared (DLD % built and dates on the register)
82.7%more than 10 points behind the time elapsed (95% interval 80 to 85.1%)
-27median gap in points, % built minus % of time elapsed (95% interval -29.1 to -26)
452projects with a projected range (10% to 99% built)
86.7%of them projected after the registered date (95% interval 83.3 to 89.5%)
≤-6098-50119-40168-30186-20140-10940291013209303401
Projects by gap between % built and % of time elapsed, in 10-point bins
Show as a table
Gap (points)Projects
-60 … -5098
-50 … -40119
-40 … -30168
-30 … -20186
-20 … -10140
-10 … 094
0 … 1029
10 … 2013
20 … 309
30 … 403
40 … 501

Projects

985 projects, page 14
Project% built (inspection)Time elapsedGap (points)PaceRegistered completionProjected rangeRegister
Soulever' by Beyond
Beyond Developments · Dubai Maritime City
0%
24 Apr 2026
3%-2.5on pace or ahead30 Dec 2028under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Barbados 1
DAMAC Properties · Al Yelayiss 1
0.2%
10 Jun 2026
3%-2.4on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Barbados 2
DAMAC Properties · Al Yelayiss 1
0.2%
10 Jun 2026
3%-2.4on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Cuba
DAMAC Properties · Al Yelayiss 1
0.2%
10 Jun 2026
3%-2.4on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Maui
DAMAC Properties · Al Yelayiss 1
0.2%
10 Jun 2026
3%-2.4on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
The First Collection at Dubai Sports City
The First Group · Dubai Sports City
65.7%
21 Sept 2026
68%-2.4on pace or ahead30 Nov 2027Jan 2028dubairealestateiq.com
Luxor by Imtiaz
Imtiaz Developments · Jumeirah Village Circle (JVC)
90%
17 Sept 2026
92%-2.3on pace or ahead15 Dec 2026Jan 2027dubairealestateiq.com
DAMAC Islands 2 - Bermuda
DAMAC Properties · Al Yelayiss 1
0.2%
10 Jun 2026
3%-2.3on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
Park Gate 2
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
55.2%
8 Jun 2026
57%-2.2on pace or ahead28 Feb 2027Mar 2027 – May 2027dubairealestateiq.com
Forest City Tower
Al Helal Al Zahaby · Majan
70.1%
13 Aug 2026
72%-2.2on pace or ahead9 Apr 2027May 2027dubairealestateiq.com
Skyhills Astra by HRE
HRE Development · Dubai Science Park
50.6%
13 Nov 2026
53%-1.9on pace or ahead30 Jun 2028Aug 2028dubairealestateiq.com
DAMAC Islands 2 - Tahiti 1
DAMAC Properties · Al Yelayiss 1
0.3%
2 Jun 2026
2%-1.7on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Tahiti 2
DAMAC Properties · Al Yelayiss 1
0.3%
2 Jun 2026
2%-1.7on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
Tavora Residences by Jhk Heights Real Estate Development
Jhk Heights · International City Ph 2 & 3
86.2%
15 Oct 2026
88%-1.5on pace or ahead15 Dec 2026Dec 2026dubairealestateiq.com
Avarra by Palace
Emaar Properties · Business Bay
0.1%
10 Jun 2026
1%-1.3on pace or ahead30 Jun 2031under 10% built: too early to projectdubairealestateiq.com
Piazza Roma
DAMAC Properties · Al Hebiah Fifth
0.2%
18 Aug 2026
1%-1.1on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
Binghatti SkyTerraces
Binghatti Developers · Motor City
0%
7 Jan 2026
1%-0.9on pace or ahead31 Oct 2027under 10% built: too early to projectdubairealestateiq.com
Salva the Heights
Emaar Properties · Al Yelayiss 5
0.5%
9 Jun 2026
1%-0.9on pace or ahead31 Jul 2030under 10% built: too early to projectdubairealestateiq.com
Sobha Estates
Sobha Realty · Bukadra
68.5%
15 Sept 2026
69%-0.9on pace or ahead31 Dec 2027Dec 2027 – Jan 2028dubairealestateiq.com
Skyscape (Sobha Hartland II)
Sobha Realty · Mohammed Bin Rashid City
38.3%
21 Sept 2026
39%-0.8on pace or ahead31 Dec 2029Sept 2028 – Feb 2030dubairealestateiq.com
Al Habtoor Tower
Al Habtoor Group · Business Bay
90%
31 Aug 2026
91%-0.6on pace or ahead31 Dec 2026Jan 2027dubairealestateiq.com
DAMAC Islands 2 - Bahamas 1
DAMAC Properties · Al Yelayiss 1
0.3%
14 May 2026
1%-0.5on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
DAMAC Islands 2 - Bahamas 2
DAMAC Properties · Al Yelayiss 1
0.3%
14 May 2026
1%-0.5on pace or ahead30 Jun 2030under 10% built: too early to projectdubairealestateiq.com
Azizi Venice 15
Azizi Developments · Madinat Al Mataar
0%
6 May 2025
1%-0.5on pace or ahead30 May 2027under 10% built: too early to projectdubairealestateiq.com
Elemental 22
Al Barari · Al Satwa
46%
4 Nov 2026
46%-0.5on pace or ahead31 May 2028Jun 2028dubairealestateiq.com
Ayamore Residence
Ayat · Palm Deira
67.6%
8 Jul 2026
68%0.1on pace or ahead7 Mar 2027Mar 2027dubairealestateiq.com
Living Legends Phase 4
Al Ghurair Investment · Majan
62.1%
13 Mar 2026
62%0.2on pace or ahead31 Mar 2027Mar 2027dubairealestateiq.com
Parkside Boulevard
Tabeer · Arjan
60.3%
28 Oct 2026
60%0.3on pace or ahead27 Dec 2027Dec 2027dubairealestateiq.com
Greenridge
Emaar Properties · Madinat Al Mataar
35.6%
17 Jun 2026
35%0.4on pace or ahead31 Dec 2028Dec 2028 – Aug 2029dubairealestateiq.com
Sunset Bay One by Imtiaz
Imtiaz Developments · Palm Deira
93.5%
2 Nov 2026
93%0.8on pace or ahead25 Dec 2026Dec 2026 – Dec 2026dubairealestateiq.com
MBL Signature
MAG · Jumeirah Lakes Towers
80%
10 Nov 2026
78%1.6on pace or ahead31 Mar 2027Mar 2027dubairealestateiq.com
Bayview
Emaar Properties · Dubai Marina
63%
14 Sept 2026
61%2.2on pace or ahead31 Jul 2028May 2028 – Aug 2028dubairealestateiq.com
Zenith Tower J1
Zenith Ventures · Jumeirah Village Circle
72.2%
4 Aug 2026
70%2.6on pace or ahead25 Dec 2026Dec 2026dubairealestateiq.com
Westar Altair
Westar Properties · Madinat Al Mataar
62.9%
20 Jul 2026
60%2.8on pace or ahead31 May 2027Apr 2027dubairealestateiq.com
Marina Shores
Emaar Properties · Dubai Marina
87.2%
14 May 2026
84%2.9on pace or ahead31 Dec 2026Nov 2026 – Dec 2026dubairealestateiq.com
Fairway Villas 2
Emaar Properties · Madinat Al Mataar
92.2%
17 Aug 2026
89%3on pace or ahead31 Dec 2026Nov 2026 – Nov 2026dubairealestateiq.com
Vida Residences Club Point
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
43.5%
3 Aug 2026
40%3.2on pace or ahead28 Feb 2029Nov 2028 – Dec 2028dubairealestateiq.com
Address Residences Dubai Creek Harbour
Emaar Properties · Dubai Creek Harbour
50.1%
16 Nov 2026
47%3.5on pace or ahead31 Jan 2029Jan 2028 – Feb 2029dubairealestateiq.com
The Valley - Elva
Emaar Properties · Al Yufrah 1
49.9%
11 Nov 2026
46%3.6on pace or ahead31 Oct 2028Jul 2028 – Sept 2028dubairealestateiq.com
Expo City Al Waha Residences 01
Expo City Dubai · Madinat Al Mataar
65.8%
26 Aug 2026
62%3.6on pace or ahead15 Jun 2027May 2027 – Jun 2027dubairealestateiq.com
Expo City Al Waha Residences 02
Expo City Dubai · Madinat Al Mataar
61.4%
26 Aug 2026
58%3.6on pace or ahead30 Jun 2027May 2027 – Aug 2027dubairealestateiq.com
Greenspoint 2
Emaar Properties · Madinat Al Mataar
40.1%
3 Aug 2026
36%3.9on pace or ahead31 Mar 2029Oct 2028 – Nov 2028dubairealestateiq.com
Mi Casa by London Gate Real Estate Development
London Gate · Jumeirah Village Circle
19.1%
21 Apr 2026
15%4.3on pace or ahead26 Oct 2028Feb 2028dubairealestateiq.com
Iridian Park 2
Object 1 · Jumeirah Village Circle
21.3%
31 Jul 2026
17%4.6on pace or ahead1 Feb 2027Dec 2026dubairealestateiq.com
Verde by Sobha
Sobha Realty · Jumeirah Lakes Towers
85%
24 Aug 2026
80%5on pace or ahead30 Jun 2027Mar 2027 – Mar 2027dubairealestateiq.com
The Valley - Venera
Emaar Properties · Al Yufrah 1
51.7%
5 Aug 2026
46%5.3on pace or ahead30 Sept 2028May 2028 – Jul 2028dubairealestateiq.com
The Valley - Velora
Emaar Properties · Al Yufrah 1
50.1%
9 Jun 2026
45%5.5on pace or ahead31 Aug 2028Mar 2028 – May 2028dubairealestateiq.com
Park Lane
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
55.4%
22 May 2026
49%6.2on pace or ahead31 Oct 2028Apr 2028 – Jun 2028dubairealestateiq.com
Roof Comfort
Roof Enterprises · Dubai Land Residence Complex
50.2%
28 Jul 2026
44%6.4on pace or ahead31 Dec 2027Sept 2027dubairealestateiq.com
The Valley - Rivana
Emaar Properties · Al Yufrah 1
95.2%
28 Oct 2026
88%7.1on pace or ahead31 Mar 2027Dec 2026 – Dec 2026dubairealestateiq.com
Greenspoint
Emaar Properties · Madinat Al Mataar
42.9%
21 Jul 2026
35%7.6on pace or ahead31 Mar 2029Jul 2028 – Jul 2028dubairealestateiq.com
Bliss Tower
Pure Bliss Development L.L.C · Dubai Land Residence Complex
92.5%
17 Sept 2026
84%8.8on pace or ahead15 Dec 2026Oct 2026dubairealestateiq.com
Creek Waters
Emaar Properties · Al Khairan First
81.1%
3 Aug 2026
72%9.1on pace or ahead30 Sept 2027Apr 2027 – May 2027dubairealestateiq.com
Parkland
Emaar Properties · Hadaeq Sheikh Mohammed Bin Rashid
50%
22 Jun 2026
40%9.9on pace or ahead30 Nov 2028Feb 2028 – May 2028dubairealestateiq.com
Wellington Grand Villas
Mbr Mansions Real Estate Development L.L.C · Majan
62.1%
14 Oct 2026
52%10.2on pace or ahead24 Jan 2028Aug 2027dubairealestateiq.com
Azra Residence
Enaam · Dubai Land Residence Complex
27.5%
21 Sept 2026
17%10.4on pace or ahead31 Dec 2027Jun 2027dubairealestateiq.com
Greenville 2
Emaar Properties · Madinat Al Mataar
47.3%
19 Jul 2026
35%12.1on pace or ahead31 Mar 2029Mar 2028 – Jul 2028dubairealestateiq.com
Azizi Zain
Azizi Developments · Jabal Ali First
80.2%
15 Oct 2026
67%13.1on pace or ahead11 Oct 2027Apr 2027 – Apr 2027dubairealestateiq.com
Azizi Riviera 54
Azizi Developments · Al Merkadh
74.6%
7 Aug 2026
61%13.6on pace or ahead30 May 2027Dec 2026 – Jan 2027dubairealestateiq.com
Ag 7even
AG Properties · Dubai Land Residence Complex
93.7%
18 Jun 2026
80%13.9on pace or ahead31 Mar 2027Sept 2026dubairealestateiq.com

Next page

Method

Time elapsed = (inspection date minus construction start on the register) divided by (registered completion date minus construction start). When no start date is printed, the registration date is used.

Gap = % built at the inspection minus % of time elapsed at the same date, in percentage points. Behind = a gap below -10 points. Registered date passed = the inspection is after the completion date on the register and the project is not at 100%.

Projection, only for 10% to 99% built: the remaining % divided by the observed pace, where the pace is % built per day since the start date, since the registration date and between the last two inspections we hold (when it rose). The range runs from the earliest to the latest of these estimates.

Limits: Construction does not move in a straight line (a slow start, faster structure, slow finishing), so a straight line from an early reading tends to give later dates than the work will need, and a late reading can give earlier ones. The % built is the DLD inspection figure, not ours.

Source: the Dubai Land Department project register as mirrored per project with its inspection history, read by our register job; 985 DLD records, 28 with two or more dated inspections.