Nov 1DATAAll 646 projects re-verified: 6,419 developer claims tested against registers, courts and pressNov 1DATAMalaysia TEDUH and Philippines DHSUD licence checks: expired licences and approved delays foundNov 1DATAThailand ONEP register: 2 condos found selling before environmental approvalNov 1DATAMexico PROFECO contract register checks: one sales registration belonged to a laundryNov 1DATAAbu Dhabi ADREC inspections and RAK RERA permit list added: % built straight from the regulatorNov 1SHIPPEDNew stage filter: completed but still sellingNov 1SHIPPEDPublic database page: verification levels, disclosure distribution, every marketNov 1DATA+212 projects in one day, round 3: USA, Caribbean, Gulf, Africa, Japan, AustraliaNov 1SHIPPEDStage on every case: off-plan or under constructionOct 31SHIPPEDVerification level per check on every case card: registry, independent, developer, contradicted
Changelog →

Kolaboro / Countries / Oman / Is it safe?

Is it safe to buy off-plan in Oman?

What the delivery record, dated promises and public documents of 14 tracked projects show.

Whether buying off-plan in Oman is safe depends on the project, and the public record differs a lot between projects. Of the 14 projects we track, 0% publish a permit or licence number, 36% state deposit protection and 1 are past the first handover date on record.

We found 24 developer claims contradicted by another source out of 117 tested. This page reports facts; it is not a rating of any company.

0%publish a permit number
36%state deposit protection
1past first handover date
14dated promises tracked
0promises broken
21%of tested claims contradicted

Delivery record#

1 of 14 projects are past the first handover date on record (median 14 months). 4 projects have a first handover date more than six months in the past, the group used for the on-time odds on the delay index.

Dated promises (handover, construction start, permits): 14 tracked, 0 kept, 0 broken, 3 moved to a later date, 10 still ahead. How promises are tracked.

What developers make public#

CheckPublicConfirmed by register or independent source
Permit or licence number0% (0)0
Deposit protection36% (5)0
Construction progress14% (2)1
Site or floor plans79% (11)0
Developer track record79% (11)6
No guaranteed-return language100% (14)0

What protects a buyer#

The protections that exist on paper only help if the project uses them: a permit you can look up, payments into an escrow or protected account in the project name, and payments tied to construction milestones you can verify. How to check a project in Oman.

Questions and answers#

Is it safe to buy off-plan property in Oman?

It depends on the project. Of 14 projects tracked by Kolaboro in Oman, 0% publish a permit number, 36% state deposit protection and 1 are past the first handover date on record (data of 5 November 2026).

How often are off-plan handovers in Oman late?

1 of 14 tracked projects are past the first handover date on record, median 14 months.

How many developer claims in Oman turned out to be contradicted?

24 of 117 tested claims (21%) were contradicted by a register or independent source.