Off-plan delays, week 48, 2026
Handover dates that moved later this week, projects past the handover date on record, and the same for earlier weeks. Same address every week, counted by code from our public data.
This week: Week 48, 2026: 23 Nov 2026 to 23 Nov 2026
Handover dates moved later (0)
No handover date moved later in this week in the records we read.
Past the handover date on record
122 projects we track are past the handover date on record and not recorded as completed (as of 23 Nov 2026). The places with the most:
| Place | Past the date on record | Longest, months |
|---|---|---|
| Bali | 25 | 8 |
| Dubai | 9 | 8 |
| Costa del Sol | 8 | 8 |
| Bangkok | 7 | 5 |
| Phuket | 7 | 5 |
| Malaysia | 6 | 5 |
| Osaka | 4 | 8 |
| Sydney | 4 | 1 |
| Abu Dhabi | 3 | 11 |
| Costa Rica | 3 | 11 |
| Melbourne | 3 | 1 |
| Vietnam | 3 | 5 |
Handover dates on record that end this month
4 projects have a handover date on record that ends in November 2026 and are not recorded as completed.
- Contour, New Jackson Manchester
- Laguna Bay Residences Malaysia
- Mont Reve Cape Town
- New residential complex near the ski lift, Bansko Bulgaria
Archive: earlier weeks
Week 47, 2026: 16 Nov 2026 to 22 Nov 2026
0 handover dates moved later.
Week 46, 2026: 9 Nov 2026 to 15 Nov 2026
2 handover dates moved later.
- Amberwood at Holland Singapore: from June 2030 to June 2033, seen 11 Nov 2026 source
- Sea Cliff by Imtiaz Dubai: from Q1 2028 to Q3 2028, seen 10 Nov 2026 source
Week 45, 2026: 2 Nov 2026 to 8 Nov 2026
11 handover dates moved later.
- Villa Peninsula Marrakech: from December 2026 to Q1 2027, seen 5 Nov 2026 source
- Amare Seafront Villas (Solare Ras El Hekma) Egypt: from Q4 2026 to Q4 2028, seen 4 Nov 2026 source
- OCEANA Wellness Residences Los Cabos: from 2023 to Q3 2026, seen 3 Nov 2026 source
- Azizi Grand Dubai: from Q4 2024 to Q1 2026, seen 3 Nov 2026 source
- Nobu Hotel and Residences Al Marjan Island Ras Al Khaimah: from Q4 2026 to Q1 2028, seen 3 Nov 2026 source
- Shivo Towers Zanzibar: from 2027 to 2028, seen 3 Nov 2026 source
- Les Vagues by Elie Saab Qatar: from Q2 2027 to Q4 2027, seen 3 Nov 2026 source
- Waldorf Astoria Hotel & Residences Miami Miami: from 2027 to Q2 2028, seen 3 Nov 2026 source
- Sur Yapı Antalya Suites Antalya: from December 2027 to June 2028, seen 3 Nov 2026 source
- Nasim Al Bahr Residences (The Luxury Collection) Ras Al Khaimah: from Q4 2027 to January 2028, seen 3 Nov 2026 source
- Cocobay Da Nang Vietnam: from October 2024 to first half of 2029, seen 2 Nov 2026 source
Week 44, 2026: 26 Oct 2026 to 1 Nov 2026
7 handover dates moved later.
- ORA by Casa Tua Miami: from 2028 to Q4 2030, seen 1 Nov 2026 source
- The Soul Fumba Zanzibar: from 2028 to 2029, seen 1 Nov 2026 source
- Amazi at Hawana Salalah Oman: from Q1 2027 to Q4 2027, seen 1 Nov 2026 source
- ORLA, Dorchester Collection Dubai: from Q2 2026 to Q4 2026, seen 1 Nov 2026 source
- Twin Tower Bulgaria: from Q2 2028 to November 2028, seen 1 Nov 2026 source
- Karl Lagerfeld Villas by Taraf Dubai: from Q2 2027 to Q3 2027, seen 1 Nov 2026 source
- South Beach Gold Coast: from second half of 2028 to Q1 2029, seen 1 Nov 2026 source
How this is counted
- A move counts when a dated copy of the developer's page, or a register, shows a handover period that starts after the period on record ends (for example Q3 2027 to 2028). A more precise date inside the same period (Q3 2027 to September 2027) is not a move.
- Past the date on record: the period on record ended before this month and the project is not recorded as completed.
- Our dated copies start in October 2026, so the archive starts there. Every week keeps this address; earlier weeks stay below.
- Facts only: a moved date is not a verdict about a developer. Each project page lists its sources and has a right of reply.
Data: the same records as /api/v1/changes and /data/promises.json (CC BY 4.0).
- Most delayed projects
- Overdue handovers by place
- What changed this week, by place
- Handover slippage: method
Made by Kolaboro (who we are). Figures are computed by code from our open data; how: method. Found an error? Corrections.
With 95% intervals
| Market | Median months late | 95% interval | n late | Past first handover | 95% interval | n with a date |
|---|---|---|---|---|---|---|
| All markets | 9.5 | 6 – 11 | 64 | 7.4% | 5.9% – 9.4% | 863 |
| Dubai | 11 | 9 – 23 | 8 | 11.3% | 5.8% – 20.7% | 71 |
| Bali | 5 | 2 – 8 | 9 | 13.6% | 7.3% – 23.9% | 66 |
Bootstrap and Wilson intervals from our dated records; a wide interval means a small sample. All intervals and the method