A disagreement between two sources is a reason to ask, not a finding: one source may be older, may describe one phase, or may round.
| Project | Field | Source A | Source B | Difference |
|---|---|---|---|---|
| UC88 Wyndham Garden BKK1 Chhun Sambath Development Co., Ltd. · Cambodia | Handover date | developer FAQ (on record 31 Oct 2026) developer FAQ: freehold title, management fee USD 1.65/sq m, 8 lifts, expected handover June 2025 | consultant monthly progress report Sep 2026 (on record 31 Oct 2026) consultant monthly progress report Sep 2026: expected completion Dec 2026, status on track | 18 months apart |
| Veranova Park (Ciudad Veranova phase 1) Arquitectura y Concreto S.A.S. · Medellín | Handover date | portal LaHaus (on record 31 Oct 2026) portal LaHaus: fiduciaria Davivienda, delivery June 2027, from COP 842.8M | portal Metrocuadrado (on record 31 Oct 2026) portal Metrocuadrado: 'sobre planos', delivery 15 Dec 2028 | 18 months apart |
| SAMANA Barari Views SAMANA Developers · Dubai | Handover date | DLD register (on record 28 Oct 2026) registered completion 2027-03-31 dubairealestateiq.com | Developer page FAQ (on record 18 Nov 2026) Developer page FAQ: "Handover is scheduled for Q2 2028." | 13 months apart |
| Skyscape (Sobha Hartland II) Sobha Realty · Dubai | Handover date | DLD register (on record 21 Sept 2026) registered completion 2029-12-31 dubairealestateiq.com | sobharealty.com (on record 18 Nov 2026) handover Dec 2028 stated for each tower (sobharealty.com) | 12 months apart |
| SAMANA Skyros SAMANA Developers · Dubai | Handover date | DLD register (on record 29 Sept 2026) registered completion 2026-04-30 dubairealestateiq.com | Developer page FAQ (on record 18 Nov 2026) Developer page FAQ: "The anticipated completion date for SAMANA Skyros is Q2 2027." | 12 months apart |
| Once Wongamat Honour Thailand · Pattaya | Handover date | agent (on record 31 Oct 2026) agent: foundations from Feb 2026, main-pillar ceremony Oct 2026, handover planned 2029 | portal (on record 31 Oct 2026) portal (Apr 2026): completion January 2028, price 7.77-59.90M | 12 months apart |
| The Brooks at Sobha Sanctuary Sobha Realty · Dubai | Handover date | DLD register (on record 15 Jul 2026) registered completion 2030-08-31 dubairealestateiq.com | A1 Properties (on record 18 Nov 2026) Trakheesi permit 1876838264 with DLD QR, from AED 4,160,000, handover Q3 2029, 60/40 (A1 Properties) | 11 months apart |
| City Walk Crestlane Meraas · Dubai | Handover date | DLD register (on record 9 Nov 2026) registered completion 2029-09-30 dubairealestateiq.com | meraas.com (on record 18 Nov 2026) payment plan PDF: starting prices 1BR AED 2.6M to 4BR duplex AED 16.3M, estimated completion Oct 2028 (meraas.com) | 11 months apart |
| SAMANA Ocean Pearl SAMANA Developers · Dubai | Handover date | DLD register (on record 17 Sept 2026) registered completion 2026-12-31 dubairealestateiq.com | Developer page FAQ (on record 18 Nov 2026) Developer page FAQ: "SAMANA Ocean Pearl is anticipated to be completed in Q4 2027." | 10 months apart |
| Kanyon by Beyond Beyond Developments · Dubai | Handover date | DLD register (on record 9 Nov 2026) registered completion 2028-09-30 dubairealestateiq.com | developer customer portal (on record 18 Nov 2026) developer customer portal: anticipated completion June 2029, 0% complete | 9 months apart |
| The Collections Vol. 2 618 Development · Bali | Handover date | partner page (on record 31 Oct 2026) partner page: handover Q3-Q4 2026, from USD 1,014,000, 11-12% ROI, 8-9 year payback | developer site (on record 31 Oct 2026) developer site: 6 villas, 3+1 bedrooms, 295 m2 living space, from IDR 16,528,200,000, completion Q1 2026 | 7 months apart |
| ORLA, Dorchester Collection Omniyat · Dubai | Handover date | DLD register (on record 21 Aug 2026) registered completion 2026-12-31 dubairealestateiq.com | developer news Feb 2024 (on record 18 Nov 2026) developer news Feb 2024: main works awarded to Innovo Build, 85 two to four bedroom homes, 3 Sky Palaces and a mansion, completion projected Q2 2026 | 6 months apart |
| Binghatti Hillviews Binghatti Developers · Dubai | Handover date | DLD register (on record 25 Jun 2026) registered completion 2026-04-01 dubairealestateiq.com | FAQ answer on the page (on record 18 Nov 2026) FAQ answer on the page: "The project is scheduled for completion in Q4 2026." | 6 months apart |
| Metropol Cube Metropol · Georgia | Handover date | developer (on record 31 Oct 2026) developer: Royal Tulip (Louvre Hotels Group) partnership; about page says Cube to be completed in 2027 | portal (on record 31 Oct 2026) portal: 332 units, 42 floors, delivery 30 Jun 2028, 48% complete, 'no title deed' yet | 6 months apart |
| Swim-up pool complex in Altıntaş (ref AYT-3204) · Antalya | Handover date | agent listing AYT-3204 (on record 30 Oct 2026) agent listing AYT-3204: from EUR 113,700 (1+1, 58 m2), completion 31 Jan 2027, prices updated 10 Feb 2026 | agent TEKCE (on record 30 Oct 2026) agent TEKCE: completion June 2027, title deed kat irtifakı (floor easement) | 5 months apart |
| Volta Tower DAMAC Properties · Dubai | Handover date | DLD register (on record 18 Aug 2026) registered completion 2027-12-31 dubairealestateiq.com | Property Finder (on record 18 Nov 2026) floor plans per unit type; construction start 14 Dec 2023, expected completion May 2028 (Property Finder) | 5 months apart |
| Sea Cliff by Imtiaz Imtiaz Developments · Dubai | Handover date | DLD register (on record 13 Oct 2026) registered completion 2028-08-15 dubairealestateiq.com | developer (on record 18 Nov 2026) developer: construction progress 7% overall, sub-structure 66%, estimated completion Q1 2028 | 5 months apart |
| One by Binghatti Binghatti Developers · Dubai | Handover date | DLD register (on record 14 May 2026) registered completion 2026-05-30 dubairealestateiq.com | FAQ answer on the page (on record 18 Nov 2026) FAQ answer on the page: "One by Binghatti is expected to be completed by Q4 2026." | 5 months apart |
| SAMANA Park Meadows SAMANA Developers · Dubai | Handover date | DLD register (on record 1 Oct 2026) registered completion 2027-08-31 dubairealestateiq.com | Developer page FAQ (on record 18 Nov 2026) Developer page FAQ: "SAMANA Park Meadows anticipated handover date is scheduled for Q1 2028." | 5 months apart |
| Shahrukhz Residences by Danube Danube Properties Development L.L.C · Dubai | Handover date | DLD register (on record 13 Aug 2026) registered completion 2029-06-30 dubairealestateiq.com | developer page (on record 18 Nov 2026) developer page: from AED 1.65m, completion Q4 2029, 30/70 plan, studio to penthouse | 4 months apart |
| AYA Beachfront Residences Deyaar Development PJSC · Umm Al Quwain | Handover date | developer construction update page (on record 31 Oct 2026) developer construction update page: shoring and services relocation 100% complete, main works imminent, completion Q4 2027 | Property Finder (on record 31 Oct 2026) Property Finder: from AED 1.095M, delivery Q2 2028 | 4 months apart |
| InterContinental Residences Bangkok Asoke CG Capital Advisory Limited · Bangkok | Handover date | launch release (on record 31 Oct 2026) launch release (Nov 2025): 88 freehold residences, 139-547 sq m, from THB 40.8M, value THB 5.5bn, completion Q2 2029 | portal (on record 31 Oct 2026) portal: 32 floors, building floor plan images by floor (6-32), unit plans 2BR, 3BR, 4BR penthouse, listed from THB 44.8M, completion Jan 2029, status off plan | 3 months apart |
| Rove Home Dubai Marina IRTH Group · Dubai | Handover date | DLD register (on record 6 Jul 2026) registered completion 2028-03-31 dubairealestateiq.com | developer page (on record 18 Nov 2026) 679 apartments, anticipated handover Q4 2027 (developer page) | 3 months apart |
Method
Each fact line of a project record names its source (a bracket at the end, or a prefix such as "press:" or "portals:"). For Dubai, the DLD register record is one more source.
Handover: two sources disagree when their dates cannot both be true (a quarter covers 3 months, a month 1, a year 12) and are at least 3 months apart. Lines about one phase, tower or building are skipped.
Units: two sources give unit counts that differ by 2 or more and by 5% or more. Lines about one phase or a mix of unit types are skipped.
Starting price: two sources give a "from" price in the same currency that differs by 10% or more. Prices change over time, so the dates are shown.
Permit numbers: our records keep one permit number per project, with the source that prints it, so there is no second value to compare yet.
Limits: Text rules can miss a disagreement or read a line wrongly; every row shows the exact lines so it can be checked.
Statistical outliers in our data are on the anomaly radar
Files: /data/n35a/contradictions.json · /open/n35a-build.py