Kolaboro / Malaysia / Prisma Bumiraya Sdn. Bhd.
Quinton
Public records and facts
Kolaboro ID: MYS-376
What is published about Quinton in Daerah Barat Daya, Pulau Pinang, Malaysia, what official registers and other sources say, and what changed over time. Facts only, each with its source.
Handover date passed Promised for April 2023. That date passed 43 months ago (as of 25 Nov 2026). Our latest research record (checked 25 Nov 2026): under construction. teduh.kpkt.gov.my Overdue handovers in Malaysia
Is it safe? What we know and what we do not: Known: permit, company, handover date, construction. Not known yet: website, official lists.
Six checks at a glance
Last checked 25 Nov 20261 source
- Permitconfirmed in a register
- Companylegal name published
- Handover datedate passed 43 mo. ago
- Constructiondeveloper updates only
- Websitenot monitored yet
- Official listsnot screened yet
Next question to ask Find the developer company in the official company register of Malaysia. All questions
What each colour means
- Green: published or confirmed.
- Amber: partly.
- Red: not published or the date passed.
- Grey: not checked yet.
Facts, not a verdict.
Quinton is listed as under construction in Daerah Barat Daya, Pulau Pinang, Malaysia, by Prisma Bumiraya Sdn. Bhd. The handover date on record is April 2023. That date passed 43 months ago, according to our records. A permit number is published. Transparency score: 100 of 100. 6 of 6 developer claims we tested are confirmed.
The 10 key facts, by where they come from Facts, not a verdict. Each value, its source and date are in the record. How we verify a fact
Confirmed 3 of 10
In an official register or by our satellite reading
- Units
- Construction progress
- Official register entry
Published, not confirmed 4 of 10
By the developer, a listing portal or another web page
- Handover date
- Permit or registration number
- Starting price
- Developer legal entity
Not found yet 3 of 10
- Escrow or deposit protection
- Satellite reading (built-up share, first > last)
- Court cases on record (developer)
Malaysian housing developer register (KPKT TEDUH)
What the official register of the Ministry of Housing and Local Government says about this project, entry by entry. Dates are those printed on the register.
- Register status
- Ailing (sick project) (Sakit)
- Construction progress (latest report)
- 71.11%
- Advertising and sales permit
- 14734-1/06-2024/0970(R)-(S) valid 3 Jun 2023 to 2 Jun 2024 expired on 2 Jun 2024
- Vacant possession due
- 12 Oct 2020 (first sale agreement 12 Oct 2017, delivery period 36 months)
- Approved extension
- 30 months approved, new date 12 Apr 2023 The date 12 Apr 2023 has passed and the register does not show completion.
- Units and price range
- 378 · RM 233,000 - RM 500,000
- Developer licence
- 14734/07-2027/0473(A) valid to 4 Jul 2027
- Source
- teduh.kpkt.gov.my read 25 Nov 2026
Register status of every Malaysian project we trackPrisma Bumiraya Sdn. Bhd.: register record across markets
Official register: Permit or licence number, Deposit protection, Construction progress · Not found: Floor or site plans, Developer track record, No guaranteed returns
- 1 source: 1 official register. Sources
- Permit check: the register entry 14734-1 (Malaysia KPKT TEDUH register, looked up 25 Nov 2026) appears in the number the developer publishes. Official register
- Reviewed on 25 Nov 2026 under review checklist n27 and method version 1.0: a desk review of public sources, no site visit. Accountable for data and method: Ignacio Hojas García-Plaza.
- Current until 23 Feb 2027: a review older than 90 days is marked out of date here.
- What we cannot know from public sources · Who pays us, conflicts of interest
- Something wrong? Use the flag button next to any line, or write to hello@kolaboro.com.
All key facts
- Location
- Daerah Barat Daya, Pulau Pinang, Malaysia
- Stage
- under construction teduh.kpkt.gov.my
- Handover on record
- April 2023 teduh.kpkt.gov.my
- Permit or licence number
- Developer licence 14734/07-2027/0473(A); Advertising and sales permit 14734-1/06-2024/0970(R)-(S) teduh.kpkt.gov.my
- Deposit protection
- stated teduh.kpkt.gov.my
- Page we read
- teduh.kpkt.gov.my teduh.kpkt.gov.my
- Last checked
- 25 Nov 2026
- Open data record
- MYS-376
One email when what is published about Quinton changes: handover date, prices, documents or register results. We check every day; first we send a link to confirm your address.
Free: a PDF report of Quinton with every fact and its source. The link appears here once you add your email. Download the free PDF report
We send a link to confirm first. Every email has a link to stop.
In short
- Quinton is listed as under construction in Daerah Barat Daya, Pulau Pinang, Malaysia, by Prisma Bumiraya Sdn. Bhd. teduh.kpkt.gov.my
- The handover date on record is April 2023. teduh.kpkt.gov.my
- That date passed 43 months ago, according to our records. promise tracker
- A permit or licence number is published. teduh.kpkt.gov.my
- Of 6 developer claims we checked: 6 confirmed by a register or an independent source, 0 not yet verified, 0 contradicted by another source. Open data record
The record field by field: 7 of 10 key facts held, each with its source and date; 3 still unknown, with how to find them.One-page brief to print
Document checklistPayment plan stress testDeveloper timelineFind a project by permit or register number
Is Quinton legit? What we could check
Transparency score 100 of 100, computed on 25 Nov 2026 from public sources. kolaboro.com
What is published and checkable about Quinton, item by item, with the source of each. This is not a verdict: Kolaboro does not label projects or developers. "Not published" means we found no public source.
Published or confirmed: 7 of 7 items we could check.
- Developer identified by legal name: Legal name: Prisma Bumiraya Sdn. Bhd. 10 of 10
- Developer found in an official company register: Not checked Not checked by us: left out of this project's total.
- Permit or licence number published: Number published: Developer licence 14734/07-2027/0473(A); Advertising and sales permit 14734-1/06-2024/0970(R)-(S) 15 of 15
- Permit confirmed by a register or independent source: Confirmed (registry) 5 of 5kolaboro.com
- Handover date published: Published: April 2023 10 of 10
- Handover date record: Not enough dated history yet Not checked by us: left out of this project's total.kolaboro.com
- Deposit protection stated: Escrow, bank guarantee or insurance stated 15 of 15
- Address or plot location published: Precise enough for a map pin 10 of 10
- Developer website health: Developer website not checked by us Not checked by us: left out of this project's total.
- Official lists screened: not screened yet Not checked by us: left out of this project's total.
- Price published: Price published 5 of 5
- page we read: teduh.kpkt.gov.my Kolaboro
How much does Quinton cost?
- Prices and payment plan as published on the pages we read (copy of 25 Nov 2026). teduh.kpkt.gov.my
- Price from: MYR 233,000 - 500,000 teduh.kpkt.gov.my
- Permit authority: KPKT / Jabatan Perumahan Negara (developer licence and advertising and sales permit) teduh.kpkt.gov.my
- Handover promised: April 2023 teduh.kpkt.gov.my
- Original handover date: October 2020 teduh.kpkt.gov.my
- 6 statements of the developer or listing are compared with the records in "Developer claims we tested".
Payment plan of Quinton
- No payment plan was published on the pages we read (read on 25 Nov 2026).
Unit types, sizes and floor plans of Quinton
- Units: 378 teduh.kpkt.gov.my
- Page read on 25 Nov 2026.
Total cost to buy at Quinton: taxes and fees
Purchase taxes and fees in Malaysia: not published in our country guide yet. Work it out with your own figures
Prices over time
We hold no dated copy of this page yet, so we cannot show its prices over time. Data as JSON
Price per m² against official data
No official comparison available for this project. The developer does not publish both a starting price and a unit size (no size found), so there is no price per m² to compare.
Compared only with official open data (registered sale prices or official appraised values). How we use data.
When will Quinton be completed?
Handover on record: April 2023, as seen on teduh.kpkt.gov.my on 25 Nov 2026.
Every dated promise we found, how it changed and whether the date has passed. Status rules: promise tracker.
- Handover date on record: April 2023. Not moved in our records. teduh.kpkt.gov.my
- No dated promise found in the sources we read.
- Handover date on record passed 43 months ago (our overdue watcher). promise tracker
- Delay stated in the sources we read: 30 months. teduh.kpkt.gov.my
Delivery forecast
Estimate from the dated handover history of comparable projects (Kaplan-Meier), not a finding about this one.
No dated handover promise in our records, so there is no forecast.
Where it should be by now
By today (25 Nov 2026), the developer's own schedule says:
- Handover or completion: due by April 2023 (3 years ago).
Add the promised dates to your calendar (.ics) Subscribe, so a moved date updates itself
Dated promises on record: 1, each with its source. A period such as a quarter is placed on its last day. These are the developer's dates, not a confirmation by Kolaboro.
Permits and licences
Permit or licence number Developer licence 14734/07-2027/0473(A); Advertising and sales permit 14734-1/06-2024/0970(R)-(S), published by teduh.kpkt.gov.my.
- Number published: Developer licence 14734/07-2027/0473(A); Advertising and sales permit 14734-1/06-2024/0970(R)-(S). teduh.kpkt.gov.my
- Official register check: Malaysia KPKT TEDUH register, advertising and sales permit: active, permit 14734-1/06-2024/0970(R)-(S) valid to 2024-06-02; progress 71.11% (checked 25 Nov 2026). kolaboro.com/registers
- Official register for Malaysia: KPKT TEDUH (opens in a browser, checked 13 Nov 2026) teduh.kpkt.gov.my
Live check in the official registers
Asks the official registers of this country now. Each answer is kept with a digital fingerprint (SHA-256), so it can be checked later.
Where is Quinton?
Location as published: Daerah Barat Daya, Pulau Pinang, Malaysia, on teduh.kpkt.gov.my (checked 25 Nov 2026).
- Area as published: Daerah Barat Daya, Pulau Pinang, Malaysia. teduh.kpkt.gov.my
- Pin on the map: from a published address or coordinates. teduh.kpkt.gov.my




Map © OpenStreetMap contributors. Pin as recorded.
The six buyer checks
4 of 6 buyer checks public, 3 confirmed by a register or an independent source (checked 25 Nov 2026). kolaboro.com
Public means the information is published. The level says who confirms it. Method: how we score.
| Check | Public | Who confirms it | What we found |
|---|---|---|---|
| Permit or licence number | yes | confirmed in an official register | |
| Deposit protection | yes | confirmed in an official register | |
| Construction progress | yes | confirmed in an official register | |
| Floor or site plans | no | not published | |
| Developer track record | no | not published | |
| No guaranteed returns | yes | not published |
Developer claims we tested
Reviewed on 25 Nov 2026: developer page or official register read, register looked up, handover date checked.
| What the developer or listing says | What the records show |
|---|---|
| KPKT TEDUH register lists advertising and sales permit 14734-1/06-2024/0970(R)-(S) for Quinton (project code 14734-1), valid 2023-06-03 to 2024-06-02 (register read 25 Nov 2026) teduh.kpkt.gov.my official register | verified Official register |
| Developer Prisma Bumiraya Sdn. Bhd. holds KPKT developer licence 14734/07-2027/0473(A) (valid 2022-05-31 to 2027-07-04); register status Digulung teduh.kpkt.gov.my official register | verified Official register |
| Register overall status "Sakit" (Malay for ailing (sick project)), construction progress 71.11% per component (latest 7(f) report in HIMS) teduh.kpkt.gov.my official register | verified Official register |
| 378 units on the register (Rumah Pangsa/Kondo), up to 16 floors teduh.kpkt.gov.my official register | verified Official register |
| Register price range for the units: RM 233,000 to RM 500,000 teduh.kpkt.gov.my official register | verified Official register |
| Sale agreement type Jadual H (Housing Development Act statutory form, stage payments into a Housing Development Account), delivery period 36 months; first sale agreement 12 October 2017, vacant possession due 12 October 2020; the register records an approved extension of 30 months, new vacant possession date 12 April 2023 teduh.kpkt.gov.my official register | verified Official register |
What changed, with dates
Last checked 25 Nov 2026.
Nothing to compare yet: changes show here once we hold a second dated copy (first copy 25 Nov 2026).
Public reports
What public sources report, with the link. We list reports; we do not judge the developer.
- No reports of disputes, regulator action, stoppages or financial difficulty found in the sources we read.
Who is the developer of Quinton?
Developer as published: Prisma Bumiraya Sdn. Bhd., on teduh.kpkt.gov.my (checked 25 Nov 2026).
- Quinton is developed by Prisma Bumiraya Sdn. Bhd., as published on the pages we read. teduh.kpkt.gov.my
- Legal entity: Prisma Bumiraya Sdn. Bhd. teduh.kpkt.gov.my
- Projects of Prisma Bumiraya Sdn. Bhd. we track: 1 (not yet completed: 1, completed: 0). kolaboro.com
- Official company register (Malaysia): KPKT TEDUH teduh.kpkt.gov.my
Alternatives to Quinton
Projects in Malaysia with a published price within 30 % of this one (same currency) and a higher transparency score (this project: 100 of 100). The score counts what is published and checkable, not a recommendation. How the transparency score works
No project in Malaysia has a similar published price and a higher transparency score.
Compared side by side
Similar projects
Closest projects with a pin: Eden At Botanica Ct (1.4 km), The Skyline (5.5 km), The Dew (5.6 km). Compare the four side by side
Market context: Malaysia
- We track 549 projects in Malaysia. 97% publish a permit or licence number and 97% state deposit protection. kolaboro.com/m/malaysia/
- In Malaysia, 47 tracked projects are past their first handover date on record: a median of 6 months (range 1 to 96). Historical statistic from our records, not a forecast. This project: 73 months past its first date on record (October 2020). How this is computed
- Delay index for Malaysia: the handover date on record moved for 10 of 15 projects with a dated promise; mean shift over all of them: 19 months; over those that moved: 28.5 months. kolaboro.com/handover
How this record compares with Malaysia, field by field
Compare with the closest projects
The three projects in the same market with the nearest handover date (same area first), with the facts we hold and how many an official register confirms.
| Project | Area | Handover date | Fields held | Confirmed by a register |
|---|---|---|---|---|
| Quinton | Daerah Barat Daya, Pulau Pinang | 2023-04 | 7 / 10 | 3 |
| Dwi@rimbun Kasia | Seremban, Negeri Sembilan | 2022-11 | 7 / 10 | 3 |
| Grenepark Village | Hulu Langat, Selangor | 2024-04 | 7 / 10 | 3 |
| Loft Saujana | Larut & Matang, Perak | 2024-06 | 7 / 10 | 3 |
Buyer reviews
There are no verified buyer reviews of Quinton yet. We publish a review only from a buyer who proves the purchase (fingerprint of the contract or receipt, signed with a passkey) and only after a moderator has read it.
Reviews waiting for moderation are not shown.
Right of reply
No reply from the developer on record (checked 25 Nov 2026).
Are you the developer? Send documents and we add your reply to this page. Found a wrong fact? Tell us and we correct it with a dated note.
Reply as the developer Report a correction Questions to ask the developer
Questions to ask the developer about Quinton
- What is the legal name and registration number of the company that sells the units and signs the contract?
- The handover date on record (April 2023) has passed. What is the new date in writing, and what compensation does the contract give?
- Can you send dated photos or the latest inspection report of the construction?
- Who owns the land, and can I see the title or lease document?
Prepare these questions as an email · All questions, with the reason for each
Before you pay
Before you sign: your checklist for Malaysia
Tick each step as you do it. Your ticks stay in this browser only.
Buyer journey for this project, from reservation to handover
Paste the project link for a free live check of what official registers say. For a full desk review, order the pre-purchase check; site visits by a local agent are on request: we confirm a local agent for your location before you pay.
What next
- Compare with similar projects
- Alert me if the date or price changes
- Ask the developer
- Timeline of every dated record
- Embed these facts on your site
Share this page: WhatsApp My projects
Questions buyers ask
Is Quinton legit?
Kolaboro does not label projects or developers. What the public record shows: A permit or licence number is published. Of 6 developer claims we checked: 6 confirmed by a register or an independent source, 0 not yet verified, 0 contradicted by another source. The handover date on record is April 2023. That date passed 43 months ago, according to our records. No reports of disputes, regulator action, stoppages or financial difficulty found in the sources we read. Published or confirmed: 7 of 7 items we could check. Transparency score: 100 of 100. Check the sources on this page and ask the developer for documents before paying.
Where is Quinton?
Quinton is in Daerah Barat Daya, Pulau Pinang, Malaysia, according to the sources listed on this page. Pin on the map: from a published address or coordinates.
When will Quinton be completed?
The handover date on record is April 2023. That date passed 43 months ago, according to our records.
Is Quinton delayed?
According to our records the handover date on record passed 43 months ago. The latest handover date on record is April 2023.
Who is the developer of Quinton?
Prisma Bumiraya Sdn. Bhd., according to the sources listed on this page.
Does Quinton have a permit or licence?
A permit or licence is confirmed in an official register (see Permits and licences).
What do buyers say about Quinton?
There are no verified buyer reviews yet. Buyers who prove their purchase can submit one; it is published after moderation.
How much does Quinton cost?
The lowest price in the sources we read is MYR 233,000 and the highest MYR 500,000. Prices are as published and can change; ask the developer for the current price list.
What is the payment plan of Quinton?
No payment plan was published on the pages we read (read on 25 Nov 2026).
What unit types and sizes does Quinton have?
As published: Units: 378.
Is Prisma Bumiraya Sdn. Bhd. a registered company?
Legal entity: Prisma Bumiraya Sdn. Bhd. Source: our research record of Quinton.
What is the transparency score of Quinton?
Transparency score: 100 of 100. It counts what is published and checkable, not quality.
When was Quinton last checked, and what changed?
Last checked 25 Nov 2026. Nothing to compare yet: changes show here once we hold a second dated copy (first copy 25 Nov 2026). No change to the published facts is recorded.
Sources
Every fact on this page links to its source. Pages we read are fingerprinted and kept by date.
- teduh.kpkt.gov.my official register
Archived copies of the page we read (Internet Archive)
Download this record: JSON · CSV · Markdown (CC BY 4.0) · Verification certificate
Last checked 25 Nov 2026. How we collect data: data policy. Facts quoted from sources are shown in the language of the source.