Register entries: 388, on 340 projects, read on 23 Nov 2026. Every value below is copied from the register; nothing is estimated. The register: teduh.kpkt.gov.my
By market
| Market | Entries | On track | Not started | Late | Completed with CCC | With extension | Median extension (months) | Date passed | Permit expires within 180 days |
|---|---|---|---|---|---|---|---|---|---|
| Malaysia | 295 | 250 | 32 | 11 | 0 | 148 | 12 | 4 | 27 |
| Kuala Lumpur | 93 | 76 | 6 | 8 | 3 | 80 | 16 | 0 | 13 |
Late or ailing counts the register statuses Lewat (late), Sakit (ailing) and Terbengkalai (abandoned). Date passed means the vacant possession date (after any approved extension) is before the day of our read and the register does not show Siap Dengan CCC (completed with certificate of completion and compliance).
Late or ailing on the register (19)
| Project | Register status | Construction progress (latest report) | Vacant possession due | Approved extension |
|---|---|---|---|---|
| Residensi ZIG | Late (Lewat) | 63.18% | 22 Jul 2026 | 16 months, to 22 Nov 2027 |
| Residensi M Azura | Late (Lewat) | 24% / 23.5% | 14 Nov 2027 | 12 months, to 14 Nov 2028 |
| Versa @ Aspen Vision City | Late (Lewat) | 70.71% / 75% | 6 Jul 2026 | 12 months, to 6 Jul 2027 |
| Residensi Naluri 30750-1 | Late (Lewat) | 26.15% / 24.79% | 10 Sept 2027 | 16 months, to 10 Jan 2029 |
| Kyliez Suites @ KL City Centre | Late (Lewat) | 28.33% | 3 Sept 2027 | 12 months, to 3 Sept 2028 |
| Penchala 188 Residency | Late (Lewat) | 68.62% | 30 May 2027 | |
| Residensi J Satin 30019-3 | Late (Lewat) | 51.18% / 67.39% | 8 Dec 2026 | 12 months, to 8 Dec 2027 |
| Residensi J Satin 30019-2 | Late (Lewat) | 61.34% | 8 Apr 2026 | 18 months, to 8 Oct 2027 |
| Residensi J Satin 30019-1 | Late (Lewat) | 75.98% / 73.46% | 1 Aug 2025 | 18 months, to 1 Feb 2027 |
| Residensi Desa Timur 30363-2 | Late (Lewat) | 57.95% | 28 Jun 2026 | 18 months, to 28 Dec 2027 |
| Coronation Square, Menara 3 | Late (Lewat) | 88.93% | 7 May 2026 | 12 months, to 7 May 2027 |
| Eden At Botanica Ct | Late (Lewat) | 39.27% | 19 Jul 2027 | |
| The Cube | Late (Lewat) | 80.1% | 17 Apr 2027 | |
| Pangsapuri Servis Permatang Janggus | Ailing (sick project) (Sakit) | 95.88% | 12 Oct 2026 | |
| Laguna Bay Residences | Ailing (sick project) (Sakit) | 96.32% | 19 Nov 2026 | |
| Pangsapuri Seri Tawar Permai | Ailing (sick project) (Sakit) | 97.5% | 3 Oct 2026 | |
| Se.duduk | Late (Lewat) | 21.29% / 22.97% / 24.08% / 24.05% / 20% | 7 Dec 2027 | 12 months, to 7 Dec 2028 |
| Pangsapuri Seri Berlian | Late (Lewat) | 87.5% | 1 Feb 2029 | |
| SOHO Amantara | Ailing (sick project) (Sakit) | 93.82% | 9 Jun 2026 |
Longest approved extensions
An approved extension moves the vacant possession date in the sale agreements; the register records the months approved and the new date.
| Project | With extension | Vacant possession due | New date | Register status | Construction progress (latest report) |
|---|---|---|---|---|---|
| Divine KLCC | 39 | 6 Jul 2029 | 6 Oct 2032 | On track (Lancar) | 5% / 5% |
| Skyline One Sentosa | 30 | 20 Sept 2028 | 20 Mar 2031 | On track (Lancar) | 9.2% / 5.95% |
| 111 Menerung (One Eleven Menerung) | 24 | 16 Feb 2025 | 16 Feb 2027 | On track (Lancar) | 95% |
| Alaia Titiwangsa | 24 | 16 Dec 2024 | 16 Dec 2026 | On track (Lancar) | 95.3% |
| Armani Hallson KLCC (Residensi Armani Hallson KLCC) | 24 | 20 Jun 2028 | 20 Jun 2030 | On track (Lancar) | 37.5% / 37.5% |
| Axis Tower | 24 | 26 Nov 2028 | 26 Nov 2030 | On track (Lancar) | 20.17% |
| Brixton Tower | 24 | 26 Nov 2028 | 26 Nov 2030 | On track (Lancar) | 20.12% |
| Dover Tower | 24 | 26 Nov 2028 | 26 Nov 2030 | On track (Lancar) | 20.1% |
| M Grand Minori 9600-7 | 24 | 25 Feb 2029 | 25 Feb 2031 | On track (Lancar) | 13.63% |
| Menara Dutamas | 24 | 30 Jul 2029 | 30 Jul 2031 | On track (Lancar) | 0% |
| Osk Areca | 24 | 24 Dec 2028 | 24 Dec 2030 | On track (Lancar) | 21.53% |
| Residensi Begonia | 24 | 15 Oct 2029 | 15 Oct 2031 | Not started (Belum Mula) | 0% |
| Residensi Bestari | 24 | 30 Jun 2029 | 30 Jun 2031 | On track (Lancar) | 5% / 5% |
| Residensi Hanya Wahyu | 24 | 15 Oct 2029 | 15 Oct 2031 | Not started (Belum Mula) | 0% / 0% |
| Residensi Komersial Pinggiran Sungai 31063-5 | 24 | 21 Aug 2029 | 21 Aug 2031 | On track (Lancar) | 5% |
| Residensi Radium Evara | 24 | 19 Sept 2029 | 19 Sept 2031 | On track (Lancar) | 5% / 0% |
| Residensi Skyone | 24 | 6 Mar 2029 | 6 Mar 2031 | On track (Lancar) | 5% / 5% / 5% |
| Suite Canselor | 24 | 9 May 2026 | 9 May 2028 | On track (Lancar) | 63.11% |
| The Lighthauz | 24 | 14 Nov 2028 | 14 Nov 2030 | On track (Lancar) | 15.06% |
| The Westin Residences Penang | 24 | 22 May 2028 | 22 May 2030 | On track (Lancar) | 34.08% |
| Bangsar Hill Park | 23 | 8 Sept 2023 | 8 Aug 2025 | Completed with CCC (Siap Dengan CCC) | 100% / 100% |
| Breeze Hill | 22 | 13 Jan 2029 | 13 Nov 2030 | On track (Lancar) | 20% |
| M Grand Minori 9600-6 | 22 | 25 Sept 2028 | 25 Jul 2030 | On track (Lancar) | 20% |
| Menara Senja | 22 | 8 Aug 2027 | 8 Jun 2029 | On track (Lancar) | 44.61% |
| Parkside Residences | 22 | 9 Mar 2028 | 9 Jan 2030 | On track (Lancar) | 20% |
Vacant possession date passed (4)
The register may lag behind the site: a passed date is a reason to ask the developer for the certificate of completion, not proof of a problem.
| Project | Date on the register | Register status | Construction progress (latest report) |
|---|---|---|---|
| SOHO Amantara | 9 Jun 2026 | Ailing (sick project) (Sakit) | 93.82% |
| Pangsapuri Seri Tawar Permai | 3 Oct 2026 | Ailing (sick project) (Sakit) | 97.5% |
| Pangsapuri Servis Permatang Janggus | 12 Oct 2026 | Ailing (sick project) (Sakit) | 95.88% |
| Laguna Bay Residences | 19 Nov 2026 | Ailing (sick project) (Sakit) | 96.32% |
Permits expiring in the next 180 days (40)
A developer may only advertise and sell units while its advertising and sales permit is valid; permits are usually renewed each year.
| Project | Advertising and sales permit | Valid to | Register status |
|---|---|---|---|
| The Loop Residences | 30557-1/12-2026/1300(N)-(S) | 6 Dec 2026 | Not started (Belum Mula) |
| Alaia Titiwangsa | 20198-1/12-2026/0884(A)-(S) | 7 Dec 2026 | On track (Lancar) |
| Residensi Mh Platinum 3 | 30581-1/12-2026/1309(A)-(S) | 9 Dec 2026 | On track (Lancar) |
| Foreshore Apartment | 30246-1/12-2026/1360(A)-(S) | 25 Dec 2026 | On track (Lancar) |
| Pangsapuri Servis Bijirin | 30059-1/12-2026/1371(A)-(S) | 27 Dec 2026 | On track (Lancar) |
| Kondominium Stellar Damansara | 30147-1/01-2027/0974(R)-(S) | 3 Jan 2027 | On track (Lancar) |
| Residensi Nuria | 30564-1/01-2027/0020(A)-(S) | 8 Jan 2027 | On track (Lancar) |
| Residensi Skyline Kuchai 30331-2 | 30331-2/01-2027/0085(R)-(S) | 15 Jan 2027 | On track (Lancar) |
| The Cube | 30515-1/01-2027/0072(A)-(S) | 19 Jan 2027 | Late (Lewat) |
| Residensi Oasis | 30524-1/01-2027/0073(A)-(S) | 21 Jan 2027 | On track (Lancar) |
| Residensi Mutiara Austin 30292-2 | 30292-2/01-2027/0090(N)-(S) | 29 Jan 2027 | On track (Lancar) |
| Residensi Newurban | 30628-1/02-2027/0166(A)-(S) | 19 Feb 2027 | On track (Lancar) |
| Raffles 188 | 30674-1/02-2027/0161(N)-(S) | 19 Feb 2027 | On track (Lancar) |
| Bon Kiara | 30079-1/02-2027/0125(R)-(S) | 20 Feb 2027 | On track (Lancar) |
| Residensi Riverville 2 | 30565-1/02-2027/0170(A)-(S) | 21 Feb 2027 | On track (Lancar) |
| Pangsapuri Seri Tawar Permai | 30084-1/02-2027/0339(R)-(S) | 22 Feb 2027 | Ailing (sick project) (Sakit) |
| Arica (Andaman, Seri Tanjung Pinang) | 20199-2/02-2027/0060(R)-(S) | 23 Feb 2027 | On track (Lancar) |
| Residensi Amira | 30485-1/02-2027/0181(N)-(S) | 25 Feb 2027 | On track (Lancar) |
| Ppam Kysa Kiara | 30276-2/02-2027/0184(A)-(S) | 26 Feb 2027 | On track (Lancar) |
| Mlima Kiara | 30276-1/02-2027/0183(A)-(S) | 26 Feb 2027 | On track (Lancar) |
| KL 48 | 30031-1/02-2027/0137(R)-(S) | 27 Feb 2027 | On track (Lancar) |
| Suria Paragon 30435-2 | 30435-2/03-2027/0206(A)-(S) | 3 Mar 2027 | On track (Lancar) |
| The Vybe@techzone | 30203-1/03-2027/0229(A)-(S) | 8 Mar 2027 | On track (Lancar) |
| The Connaught One | 10555-15/03-2027/0216(R)-(S) | 13 Mar 2027 | On track (Lancar) |
| Residensi Amika | 20185-3/03-2027/0245(N)-(S) | 14 Mar 2027 | On track (Lancar) |
| Avion | 30544-1/03-2027/0250(A)-(S) | 19 Mar 2027 | On track (Lancar) |
| Residensi Sentral @ Putrajaya Presint 7 | 30605-1/03-2027/0266(A)-(S) | 26 Mar 2027 | On track (Lancar) |
| Ppam Brickfields | 30272-1/04-2027/0276(R)-(S) | 3 Apr 2027 | On track (Lancar) |
| Laman Sunway 1 20231-4 | 20231-4/04-2027/0294(N)-(S) | 3 Apr 2027 | On track (Lancar) |
| Lightwater Residences | 19902-2/04-2027/0306(A)-(S) | 7 Apr 2027 | On track (Lancar) |
| The Atera 30161-2 | 30161-2/04-2027/0314(A)-(S) | 15 Apr 2027 | As printed () |
| Senze @ PICC | 10294-4/04-2027/0323(A)-(S) | 17 Apr 2027 | On track (Lancar) |
| Kiaramas deDaun 8164-5 | 8164-5/04-2027/0322(A)-(S) | 17 Apr 2027 | On track (Lancar) |
| Rimbun Saujana Residency | 30619-1/04-2027/0347(A)-(S) | 25 Apr 2027 | On track (Lancar) |
| Jesselton Courtyard | 2674-7/05-2027/0364(A)-(S) | 2 May 2027 | On track (Lancar) |
| Laguna Bay Residences | 30175-1/05-2027/0438(A)-(S) | 7 May 2027 | Ailing (sick project) (Sakit) |
| Foreshore Residence | 30185-1/05-2027/0311(R)-(S) | 16 May 2027 | On track (Lancar) |
| SOHO Amantara | 30191-1/05-2027/0366(A)-(S) | 17 May 2027 | Ailing (sick project) (Sakit) |
| Penchala 188 Residency | 30514-1/05-2027/0436(N)-(S) | 19 May 2027 | Late (Lewat) |
| The Lume @ Andaman Island | 20199-5/05-2027/0445(A)-(S) | 20 May 2027 | On track (Lancar) |
All register entries as JSON · Build script · Markets compared on the 10 key facts · Kuala Lumpur · Malaysia
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a fact · Data file · Build script · /registers/