Home / Data / Delays by market
Delays by market
Three things we measure about handover delays in each market, with the projects behind every number: dates moved later in our daily copies, dates that have passed while the register shows building unfinished, and the Malaysian register's own status.
Data of 23 Nov 2026
How each number is measured
- Date moved: we compare the handover date on each record across 10 daily copies from 7 Nov 2026 to 20 Nov 2026. A move counts only when the value changes, not when the same date is written more precisely.
- Date passed: the handover date on record is before today and the official register (Dubai DLD or Malaysia KPKT) gives construction progress below 100%.
- Register status: the Malaysian housing register (KPKT TEDUH) labels each phase on track, not started, late, ailing, abandoned or completed; we count phases as the register labels them.
These are records, not predictions. Our daily copies cover a short window, so only recent moves are counted here.
Markets with 5+ dated handovers
Biggest moves later (20 of 20)
| Project | Market | Before | After | Change | Seen on |
|---|---|---|---|---|---|
| The Meriva Collection (Meriva Gardens / Meriva Signature) | Dubai | 2030-Q2 | 31 Dec 2031 | 18 mo. later | 18 Nov 2026 |
| Residensi M Terra | Malaysia | August 2027 | 2028 | 16 mo. later | 13 Nov 2026 |
| The Highgrove | Dubai | 2027-Q4 | 31 Dec 2028 | 12 mo. later | 18 Nov 2026 |
| Skyscape (Sobha Hartland II) | Dubai | 2028-Q4 | 31 Dec 2029 | 12 mo. later | 18 Nov 2026 |
| The Brooks at Sobha Sanctuary | Dubai | 2029-Q3 | 31 Aug 2030 | 11 mo. later | 18 Nov 2026 |
| City Walk Crestlane | Dubai | 2028-Q4 | 30 Sept 2029 | 9 mo. later | 18 Nov 2026 |
| Binghatti Starfall | Dubai | 2027-Q4 | 30 Sept 2028 | 9 mo. later | 18 Nov 2026 |
| Keturah Reserve | Dubai | 2026-Q4 | 30 Jun 2027 | 6 mo. later | 18 Nov 2026 |
| Ellington Sands I | Dubai | 2028-Q2 | 31 Dec 2028 | 6 mo. later | 18 Nov 2026 |
| Sea Cliff by Imtiaz | Dubai | 2028-Q1 | 15 Aug 2028 | 5 mo. later | 18 Nov 2026 |
| SAMANA Barari Avenue | Dubai | 2028-Q2 | 31 Oct 2028 | 4 mo. later | 18 Nov 2026 |
| Cove Boulevard by Imtiaz | Dubai | 2028-Q2 | 30 Oct 2028 | 4 mo. later | 18 Nov 2026 |
| Hythe by Botanica | Phuket | 2026-Q4 | 30 Apr 2027 | 4 mo. later | 13 Nov 2026 |
| SAMANA Business Hub | Dubai | 2029-Q2 | 30 Sept 2029 | 3 mo. later | 18 Nov 2026 |
| Rove Home Dubai Marina | Dubai | 2027-Q4 | 31 Mar 2028 | 3 mo. later | 18 Nov 2026 |
| Naya at District One | Dubai | 2027-Q2 | 30 Sept 2027 | 3 mo. later | 18 Nov 2026 |
| Luxor by Imtiaz | Dubai | 2026-Q3 | 15 Dec 2026 | 3 mo. later | 18 Nov 2026 |
| Sunset Bay Grand by Imtiaz | Dubai | 2027-Q4 | 15 Feb 2028 | 2 mo. later | 18 Nov 2026 |
| Pearl House 4 by Imtiaz | Dubai | 2027-Q4 | 29 Feb 2028 | 2 mo. later | 18 Nov 2026 |
| Cove Edition 4 by Imtiaz | Dubai | 2026-Q4 | 21 Jan 2027 | 1 mo. later | 18 Nov 2026 |
Handover date passed, register shows building unfinished (22)
Each row shows the date on record and the construction progress the register published, with the date we read it.
What changed this weekMalaysia: register status of every project we trackHandover pipeline by yearData file
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/