Home / Data / Changes to key facts, all projects / What changed this week

What changed this week

Every real change of a key fact in the last 7 days, grouped by market, with before and after values. Each project links to its fact timeline.

Data of 23 Nov 2026

Changes: 58, on 58 projects in 4 markets, 17 Nov 2026 to 23 Nov 2026 (the 7 days before: 10).

Dubai: this week

Changes: 55, on 55 projects. Handover dates among them: 54.

DayProjectFieldBeforeAfter
23 Nov 2026Palm Jebel Ali - Frond A VillasConstruction progress11.08%51.34%
18 Nov 2026Arancia Yards by BeyondHandover date (5 mo. earlier)2029-Q130 Oct 2028
18 Nov 2026Azizi GrandHandover date (19 mo. earlier)2026-Q32 Feb 2025
18 Nov 2026Binghatti HillviewsHandover date (8 mo. earlier)2026-Q41 Apr 2026
18 Nov 2026Binghatti StarfallHandover date (9 mo. later)2027-Q430 Sept 2028
18 Nov 2026Canal Crown de GRISOGONOHandover date (10 mo. earlier)2027-Q428 Feb 2027
18 Nov 2026Canal Heights 2 de GRISOGONOHandover date (6 mo. earlier)2027-Q331 Mar 2027
18 Nov 2026Canal Heights de GRISOGONOHandover date (6 mo. earlier)2027-Q231 Dec 2026
18 Nov 2026City Walk CrestlaneHandover date (9 mo. later)2028-Q430 Sept 2029
18 Nov 2026Couture by CavalliHandover date (25 mo. earlier)2027-Q231 May 2025
18 Nov 2026Cove Boulevard by ImtiazHandover date (4 mo. later)2028-Q230 Oct 2028
18 Nov 2026Cove Edition 4 by ImtiazHandover date (1 mo. later)2026-Q421 Jan 2027
18 Nov 2026ELAR1S Sky (Elaris Sky)Handover date (3 mo. earlier)2028-Q430 Sept 2028
18 Nov 2026Ellington Sands IHandover date (6 mo. later)2028-Q231 Dec 2028
18 Nov 2026ELO 3 (DAMAC Hills 2)Handover date (3 mo. earlier)2027-Q330 Jun 2027
18 Nov 2026Kanyon by BeyondHandover date (9 mo. earlier)2029-Q230 Sept 2028
18 Nov 2026Kensington Gardens (Greenwood)Handover date (3 mo. earlier)2027-Q427 Sept 2027
18 Nov 2026Keturah ReserveHandover date (6 mo. later)2026-Q430 Jun 2027
18 Nov 2026Luxor by ImtiazHandover date (3 mo. later)2026-Q315 Dec 2026
18 Nov 2026Mar CasaHandover date (14 mo. earlier)2027-Q431 Oct 2026
18 Nov 2026Nad Al Sheba Gardens Phase 7Handover date (7 mo. earlier)2028-Q315 Feb 2028
18 Nov 2026Naya at District OneHandover date (3 mo. later)2027-Q230 Sept 2027
18 Nov 2026One by BinghattiHandover date (7 mo. earlier)2026-Q430 May 2026
18 Nov 2026Pearl House 4 by ImtiazHandover date (2 mo. later)2027-Q429 Feb 2028
18 Nov 2026Reportage Hills (R. Hills)Handover date (6 mo. earlier)2028-Q430 Jun 2028
18 Nov 2026Rove Home Dubai MarinaHandover date (3 mo. later)2027-Q431 Mar 2028
18 Nov 2026SAMANA Barari AvenueHandover date (4 mo. later)2028-Q231 Oct 2028
18 Nov 2026SAMANA Barari LagoonsHandover date (6 mo. earlier)2028-Q331 Mar 2028
18 Nov 2026SAMANA Barari ViewsHandover date (15 mo. earlier)2028-Q231 Mar 2027
18 Nov 2026SAMANA Business HubHandover date (3 mo. later)2029-Q230 Sept 2029
18 Nov 2026SAMANA Hills South 3Handover date (4 mo. earlier)2028-Q431 Aug 2028
18 Nov 2026SAMANA IbizaHandover date (4 mo. earlier)2028-Q228 Feb 2028
18 Nov 2026Samana Imperial GardenHandover date (3 mo. earlier)2029-Q131 Dec 2028
18 Nov 2026SAMANA Ivy Gardens 2Handover date (12 mo. earlier)2028-Q431 Dec 2027
18 Nov 2026SAMANA Manhattan 2Handover date (13 mo. earlier)2027-Q41 Nov 2026
18 Nov 2026SAMANA Mykonos SignatureHandover date (11 mo. earlier)2027-Q130 Apr 2026
18 Nov 2026Samana Ocean CrestHandover date (6 mo. earlier)2028-Q430 Jun 2028
18 Nov 2026SAMANA Ocean PearlHandover date (12 mo. earlier)2027-Q431 Dec 2026
18 Nov 2026SAMANA Ocean Pearl 2Handover date (9 mo. earlier)2027-Q431 Mar 2027
18 Nov 2026SAMANA Park MeadowsHandover date (7 mo. earlier)2028-Q131 Aug 2027
18 Nov 2026SAMANA ResortsHandover date (4 mo. earlier)2028-Q330 May 2028
18 Nov 2026SAMANA SkyrosHandover date (14 mo. earlier)2027-Q230 Apr 2026
18 Nov 2026SAMANA South HavenHandover date (6 mo. earlier)2029-Q231 Dec 2028
18 Nov 2026SAMANA WavesHandover date (11 mo. earlier)2027-Q115 Apr 2026
18 Nov 2026SAMANA Waves 2Handover date (18 mo. earlier)2027-Q320 Mar 2026
18 Nov 2026Sea Cliff by ImtiazHandover date (5 mo. later)2028-Q115 Aug 2028
18 Nov 2026Shahrukhz Residences by DanubeHandover date (6 mo. earlier)2029-Q430 Jun 2029
18 Nov 2026Skyscape (Sobha Hartland II)Handover date (12 mo. later)2028-Q431 Dec 2029
18 Nov 2026Sola ResidencesHandover date (3 mo. earlier)2027-Q415 Sept 2027
18 Nov 2026Sunset Bay Grand by ImtiazHandover date (2 mo. later)2027-Q415 Feb 2028
18 Nov 2026The Brooks at Sobha SanctuaryHandover date (11 mo. later)2029-Q331 Aug 2030
18 Nov 2026The HighgroveHandover date (12 mo. later)2027-Q431 Dec 2028
18 Nov 2026The Meriva Collection (Meriva Gardens / Meriva Signature)Handover date (18 mo. later)2030-Q231 Dec 2031
18 Nov 2026Valencia (DAMAC Lagoons District)Handover date (19 mo. earlier)2029-Q328 Feb 2028
18 Nov 2026Volta TowerHandover date (6 mo. earlier)2028-Q231 Dec 2027

All changes in Dubai · Atom feed

Gold Coast: this week

Changes: 1, on 1 project. Handover dates among them: 0.

DayProjectFieldBeforeAfter
20 Nov 2026LumaraDeveloper legal entity5Point Projects Pty Ltd, ABN 61 615 602 027 (JV with Bourke Projects)5Point Projects Pty Ltd, ABN 61 615 602 027, and Bourke Projects Pty Ltd, ABN 48 061 567…

All changes in Gold Coast · Atom feed

Ho Chi Minh City: this week

Changes: 1, on 1 project. Handover dates among them: 0.

DayProjectFieldBeforeAfter
18 Nov 2026Eaton ParkEscrow or deposit protectionNo guaranteeing bank or bank-guarantee certificate published, although Vietnamese law…Developer lists bank guarantee commitments; Fili details the BIDV guarantee (up to VND…

All changes in Ho Chi Minh City · Atom feed

Sydney: this week

Changes: 1, on 1 project. Handover dates among them: 0.

DayProjectFieldBeforeAfter
20 Nov 2026WaterstoneDeveloper legal entitySekisui House Australia (subsidiary of Sekisui House Ltd)Sekisui House Australia Holdings Pty Limited, ABN 71 134 688 510 (printed on…

All changes in Sydney · Atom feed

Satellite readings and court cases carry their own dates in the table above; they are not part of the daily copies. Changes to key facts, all projects · Atom feed · JSON · Data file

Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a fact · Data file · Build script · /registers/

Protect my purchase