Off-plan projects in Turkey
1 off-plan projects tracked in Turkey. Of the reviewed ones, on average 1.0 of 6 buyer checks public; 0% publish a permit number and 0% deposit protection. Updated 2026-11-20.
- Ege Yapı Kekliktepe (Urla, İzmir, Ege Yapı; handover on record 2026): under construction, 1/6 public, 0/6 confirmed
All projects in Turkey · How to check a project in Turkey · Most delayed projects · Official registers
Handover slippage in Turkey
In Turkey, fewer than 5 projects are past their first handover date on record. Across all markets: a median of 8 months past (125 projects).
Delivery forecast: Turkey
Estimate from the dated handover history of comparable projects (Kaplan-Meier), not a finding about this one.
For context only, all markets pooled: 116 projects whose first promised handover has passed; 19 recorded as handed over. This is not an estimate for Turkey. Kolaboro promise history, 18 Nov 2026
| Handed over by | Estimated chance | 95% range |
|---|---|---|
| the first promised date | 11% | 5% - 17% |
| 6 months after it | 15% | 8% - 21% |
| 12 months after it | 19% | 10% - 27% |
| 18 months after it | 19% | 10% - 27% |
| 24 months after it | 19% | 10% - 27% |
Limitation: most projects we track are still on sale, so projects that handed over on time before we started tracking are under-represented. The estimate is likely to be too low.