Kolaboro / Countries / Australia / Cairns
Off-plan projects in Cairns, Australia
1 off-plan projects tracked in Cairns. Of the reviewed ones, on average 1.0 of 6 buyer checks public; 0% publish a permit number and 0% deposit protection. Updated 2026-11-23.
- The Davidson by Gurner (Port Douglas, Queensland, GURNER; handover on record Late 2030): off-plan, 1/6 public, 0/6 confirmed
All projects in Australia · How to check a project in Australia · Most delayed projects · Official registers
Handover slippage in Cairns
In Cairns, fewer than 5 projects are past their first handover date on record. Across all markets: a median of 5 months past (213 projects).
How this is computed · Data as JSON · Compare Cairns with other markets
Delivery forecast: Cairns
Estimate from the dated handover history of comparable projects (Kaplan-Meier), not a finding about this one.
For context only, all markets pooled: 116 projects whose first promised handover has passed; 19 recorded as handed over. This is not an estimate for Cairns. Kolaboro promise history, 18 Nov 2026
| Handed over by | Estimated chance | 95% range |
|---|---|---|
| the first promised date | 11% | 5% - 17% |
| 6 months after it | 15% | 8% - 21% |
| 12 months after it | 19% | 10% - 27% |
| 18 months after it | 19% | 10% - 27% |
| 24 months after it | 19% | 10% - 27% |
Limitation: most projects we track are still on sale, so projects that handed over on time before we started tracking are under-represented. The estimate is likely to be too low.
Follow changes: Every change to the data (JSON Feed) · What we shipped (RSS)