Kolaboro / By handover year / All places / Overdue handovers in Bangkok: November 2026 report

Overdue handovers in Bangkok: November 2026 report

Every project we track in Bangkok whose handover date on record has passed and that is not recorded as completed. Facts only, each with its source, no verdicts.

7Past the date on record
45Projects with a handover date
5Median months past
5Longest, months

Projects past the handover date

ProjectDeveloperHandover date on recordMonths pastStage, latest recordLast checked
COBE Kaset-SripatumSC Asset Corporation PCLQ2 2026 rumavi.com5Off-plan22 Nov 2026
Culture ThonglorAnanda Development PCLQ2 2026 rumavi.com5Off-plan21 Nov 2026
Escent BangnaCentral Pattana PCLQ2 2026 rumavi.com5Off-plan22 Nov 2026
Modiz Vault Kaset-SripatumAssetWise Co., Ltd.Q2 2026 rumavi.com5Off-plan22 Nov 2026
Niche Pride EkkamaiSena Development PCLQ2 2026 rumavi.com5Off-plan21 Nov 2026
Good Day Sukhumvit 93APQ3 2026 rumavi.com2Off-plan22 Nov 2026
The Base Ratchada 19Sansiri PCLQ3 2026 rumavi.com2Off-plan22 Nov 2026

Data as of 22 Nov 2026 from our open files. named.json · promises.json · bali-cases.json

How this report is made

Rule: the handover date on record (the latest one we hold) ended before November 2026; a quarter or year counts from its last month. Projects recorded as completed, or whose handover promise is recorded as kept, are left out. A passed date is a fact about the published schedule, not a finding about the developer: ask them for the current schedule in writing.

How to cite this report

Kolaboro, "Overdue handovers in Bangkok: November 2026 report", https://kolaboro.com/handover/overdue/bangkok/, data as of 23 Nov 2026. Licence CC BY 4.0.

All placesHandover years in Bangkok:2026202720282029All projects in Bangkok

Questions

How many off-plan projects in Bangkok are past their handover date?

As of 23 Nov 2026: 7 of the 45 projects we track there with a handover date on record.

Which project in Bangkok is furthest past its handover date?

COBE Kaset-Sripatum: the handover date on record is Q2 2026, 5 months ago.

Does a passed handover date mean the project has failed?

No. It means the published date has passed and the sources we read do not record the project as completed. Ask the developer for the current schedule in writing.

Are you the developer? Send us documents for anything we missed and we add them after review.

Send a reply Report a correction

Made by Kolaboro (who we are). Figures are computed by code from our open data; how: method. Found an error? Corrections.