Home / Developers / Arada / Arada: every project by handover date
Arada: every project by handover date
One timeline across all the developer's projects we track: the handover date on record, construction progress, starting price and every handover move we saw in our daily copies.
Data of 25 Nov 2026
Arada: 13 projects, 8 with a handover date on record, 1 of those dates already passed, 0 projects with a handover move in our daily copies.
2026 (1)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Jouri Hills | Dubai | 30 Jun 2026 Official register | 78.47% |
2027 (1)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Armani Beach Residences at Palm Jumeirah | Dubai | 31 Dec 2027 Official register | 10.17% | AED 23,000,000 |
2028 (4)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Nesba at Aljada | Sharjah | Q2 2028 Developer site | |||
| Safa at Aljada | Sharjah | Q2 2028 Developer site | |||
| The Gate 3-4 at Aljada | Sharjah | Q2 2028 Developer site | |||
| W Residences at Dubai Harbour | Dubai | 31 Dec 2028 Official register | 3.99% | AED 3,800,000 |
2029 (1)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Akala Hotels & Residences | Dubai | 31 Oct 2029 Official register | 1.88% | AED 3,790,000 |
2030 (1)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Inaura Hotels & Residences | Dubai | 14 Jun 2030 Official register | 1.32% | AED 3,500,000 |
No handover date on record (5)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Dalia at Masaar 3 | Sharjah | AED 2,070,000 | |||
| Jenna (Aljada) | Sharjah | ||||
| Layan at Masaar 3 | Sharjah | ||||
| Masaar 2 | Sharjah | mid-2028 Developer site | |||
| The Gate 6 at Aljada | Sharjah | AED 970,000 |
A move is a handover date that changed between two of our daily copies of the record; the date in brackets is when we saw it.
AradaDevelopers compared by register-confirmed factsCompare up to 4 developers side by side
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/