Pavilion Damansara Heights Phase 2 (Royal Suites and Imperial Residences): the record, field by field

The 10 facts a buyer checks first, each with its source and the date we read it; what we still do not know and how to find it; and how this record compares with its market.

Data of 25 Nov 2026

Back to the project page · 9 of 10 fields held. · This record as JSONOne-page brief to print

What we hold, field by field

FieldWhat we holdSourceReadAge, days
Handover date2030-Q2Web page theedgemalaysia.com5 Nov 202620
Permit or registration number30216-1/10-2028/0847(A)-(S); 30216-2/01-2029/0022(A)-(S)Web page theedgemalaysia.com5 Nov 202620
Units644Official register teduh.kpkt.gov.my23 Nov 20262
Starting priceMYR 754,000Web page theedgemalaysia.com5 Nov 202620
Developer legal entityJendela Mayang Sdn Bhd 201301035983 (1065811-D)Our record Our record: the sources are listed on the project page.5 Nov 202620
Escrow or deposit protectionNo HDA bank named; TEDUH lists Jadual H (Schedule H) sale agreements; APDL names CIMB Investment Bank Berhad as land encumbrancerOur record Our record: the sources are listed on the project page.5 Nov 202620
Construction progress56.36% to 60.08%Official register teduh.kpkt.gov.my23 Nov 20262
Satellite reading (built-up share, first > last)63% > 53%Our satellite reading /satellite/construction-index/19 Oct 202637
Official register entryMalaysia KPKT TEDUH register: advertising and sales permit (active)Official register teduh.kpkt.gov.my23 Nov 20262
Court cases on record (developer)Not heldNot held

Every dated fact on this record was read in the last 180 days. Facts read more than 180 days ago are marked for a new check. Court cases show the date of the latest case, not a read date. Construction progress is dated by the last register inspection, the satellite reading by its scene.

Malaysian housing developer register (KPKT TEDUH)

What the official register of the Ministry of Housing and Local Government says about this project, entry by entry. Dates are those printed on the register.

Register entry 30216-2

Register status
On track (Lancar)
Construction progress (latest report)
60.08%
Vacant possession due
9 Apr 2029 (first sale agreement 9 Apr 2026, delivery period 36 months)
Approved extension
16 months approved, new date 9 Aug 2030
Units and price range
490 · RM 754,000 - RM 4,666,000
Source
teduh.kpkt.gov.my read 23 Nov 2026

Register entry 30216-1

Register status
On track (Lancar)
Construction progress (latest report)
56.36%
Vacant possession due
21 Nov 2028 (first sale agreement 21 Nov 2025, delivery period 36 months)
Approved extension
16 months approved, new date 21 Mar 2030
Units and price range
154 · RM 5,429,000 - RM 19,812,000
Source
teduh.kpkt.gov.my read 23 Nov 2026

Register status of every Malaysian project we trackJendela Mayang Sdn. Bhd.: register record across markets

Fact timeline

When each key fact first entered our record and every later change, read from the dated, hash-chained daily copies of our project file (7 Nov 2026 to 20 Nov 2026).

FieldDayWhat happenedWhat we hold
Handover date7 Nov 2026In our first daily copy2030-Q2
Permit or registration number7 Nov 2026In our first daily copy30216-2/01-2029/0022(A)-(S)
Permit or registration number18 Nov 2026Changed30216-1/10-2028/0847(A)-(S); 30216-2/01-2029/0022(A)-(S)
Units25 Nov 2026First seen644
Starting price7 Nov 2026In our first daily copyMYR 754,000
Developer legal entity7 Nov 2026In our first daily copyJendela Mayang Sdn Bhd 201301035983 (1065811-D)
Escrow or deposit protection7 Nov 2026In our first daily copyNo HDA bank named; TEDUH lists Jadual H (Schedule H) sale agreements; APDL names CIMB Investment Bank Berhad as land encumbrancer
Construction progress25 Nov 2026First seen56.36% to 60.08%
Official register entry25 Nov 2026First seenMalaysia KPKT TEDUH register: advertising and sales permit (active)

1 fact changed after it was first seen: Permit or registration number.

Satellite readings and court cases carry their own dates in the table above; they are not part of the daily copies. Daily copies and their hashesData fileBuild script

What we still do not know (1)

For each missing fact: where an official source can confirm it, or what to ask the developer for in writing.

  1. Court cases on record (developer). Search the court's public judgment database for the developer's legal name; no case is on our record.

Questions to ask the developer

Market context: Malaysia

This record holds 9 of 10 fields. The median record in Malaysia holds 7 of 10 (549 projects). No record there holds more fields than this one.

Handover dates of Jendela Mayang Sdn. Bhd.: moved on 0 of 1 project in our daily copies

Fingerprint of this record

SHA-256 of the facts above in canonical JSON (keys sorted, no spaces). The same value is in record.json as sha256_facts; if any fact, source or date changes, the fingerprint changes.

2774107fdb03c6804ec9d2b94a2ca70a035b632922694e19df724806449ec279

The check downloads record.json, sorts its keys and hashes the facts on your device. Schema of the file: record.schema.json

Data validationQuery the records by URLPossible duplicate recordsSource status by siterecords.ndjsonchanges.csvJSON Schema

Where our records are thin, by market and fieldChanges to key facts, all projects

Document checklistPayment plan stress testDeveloper timelineFind a project by permit or register numberPavilion Damansara Heights Phase 2 (Royal Suites and Imperial Residences)

Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/