Home / Projects / Aspira Hills (Phases 3B and 4) / Aspira Hills (Phases 3B and 4): payment plan against late handover

Aspira Hills (Phases 3B and 4): payment plan against late handover

How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.

Data of 25 Nov 2026

Starting price on record: MYR 1,087,500 (read 12 Nov 2026). Converted at the ECB reference rate of 25 Nov 2026. ecb.europa.eu

Handover on record: August 2027 (Developer site, read 12 Nov 2026). Malaysia has too few measured moves, so the moves below are from all 20 later handover dates we measured across markets.

If handover movesHandoverMonths from todayPaid before handoverCost of the extra wait
On the date on recordAug 20279MYR 652,500
By the median move (5 months)Jan 202814MYR 652,500
By 9 in 10 moves or less (16 months)Dec 202825MYR 652,500
By the longest move measured (18 months)Feb 202927MYR 652,500

No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.

Delays by marketMore buyer tools

Document checklistDeveloper timelineFind a project by permit or register numberAspira Hills (Phases 3B and 4)

Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/