Home / Projects / Sportz by Danube / Sportz by Danube: payment plan against late handover

Sportz by Danube: payment plan against late handover

How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.

Data of 25 Nov 2026

Starting price on record: AED 661,000 (read 25 Nov 2026). Converted at the ECB reference rate of 24 Nov 2026. ecb.europa.eu

Handover on record: 30 Mar 2026 (Official register, read 25 Nov 2026). Moves below are from 18 later handover dates we measured in Dubai.

If handover movesHandoverMonths from todayPaid before handoverCost of the extra wait
On the date on recordMar 20260AED 396,600
By the median move (5 months)Aug 20260AED 396,600
By 9 in 10 moves or less (12 months)Mar 20274AED 396,600
By the longest move measured (18 months)Sept 202710AED 396,600

The handover date on record has already passed. Ask the developer for the current date and the register status before you pay more.

No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.

Delays by marketMore buyer tools

Document checklistDeveloper timelineFind a project by permit or register numberSportz by Danube

Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/

Protect my purchase