Shift Esperanza (El Pochote, Los Nidos condos): payment plan against late handover

How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.

Data of 25 Nov 2026

Starting price on record: USD 179,000 (read 31 Oct 2026). Converted at the ECB reference rate of 25 Nov 2026. ecb.europa.eu

Handover on record: 2027-Q2 (Developer site, read 31 Oct 2026). Costa Rica has too few measured moves, so the moves below are from all 20 later handover dates we measured across markets.

If handover movesHandoverMonths from todayPaid before handoverCost of the extra wait
On the date on recordJun 20277US$107,400
By the median move (5 months)Nov 202712US$107,400
By 9 in 10 moves or less (16 months)Oct 202823US$107,400
By the longest move measured (18 months)Dec 202825US$107,400

No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.

Delays by marketMore buyer tools

Document checklistDeveloper timelineFind a project by permit or register numberShift Esperanza (El Pochote, Los Nidos condos)

Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/

Protect my purchase