Residensi Kerinchi Ria: payment plan against late handover
How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.
Data of 25 Nov 2026
Starting price on record: MYR 300,000 (read 25 Nov 2026). Converted at the ECB reference rate of 24 Nov 2026. ecb.europa.eu
Handover on record: 2029-01 (Web page, read 25 Nov 2026). Kuala Lumpur has too few measured moves, so the moves below are from all 20 later handover dates we measured across markets.
| If handover moves | Handover | Months from today | Paid before handover | Cost of the extra wait |
|---|---|---|---|---|
| On the date on record | Jan 2029 | 26 | MYR 180,000 | |
| By the median move (5 months) | Jun 2029 | 31 | MYR 180,000 | |
| By 9 in 10 moves or less (16 months) | May 2030 | 42 | MYR 180,000 | |
| By the longest move measured (18 months) | Jul 2030 | 44 | MYR 180,000 |
No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.
Delays by marketMore buyer tools
Document checklistDeveloper timelineFind a project by permit or register numberResidensi Kerinchi Ria
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/