Home / Projects / Residensi Alam Permai / Residensi Alam Permai: payment plan against late handover

Residensi Alam Permai: payment plan against late handover

How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.

Data of 25 Nov 2026

Starting price on record: MYR 288,300 (read 25 Nov 2026). Converted at the ECB reference rate of 24 Nov 2026. ecb.europa.eu

Handover on record: 2030-01 (Web page, read 25 Nov 2026). Malaysia has too few measured moves, so the moves below are from all 20 later handover dates we measured across markets.

If handover movesHandoverMonths from todayPaid before handoverCost of the extra wait
On the date on recordJan 203038MYR 172,980
By the median move (5 months)Jun 203043MYR 172,980
By 9 in 10 moves or less (16 months)May 203154MYR 172,980
By the longest move measured (18 months)Jul 203156MYR 172,980

No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.

Delays by marketMore buyer tools

Document checklistDeveloper timelineFind a project by permit or register numberResidensi Alam Permai

Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/

Protect my purchase