Luxury residential complex, Vidal (Novigrad): payment plan against late handover
How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.
Data of 25 Nov 2026
Starting price on record: EUR 469,000 (read 30 Oct 2026). Converted at the ECB reference rate of 24 Nov 2026. ecb.europa.eu
Handover on record: 2025-Q3 (Web page, read 30 Oct 2026). Croatia has too few measured moves, so the moves below are from all 20 later handover dates we measured across markets.
| If handover moves | Handover | Months from today | Paid before handover | Cost of the extra wait |
|---|---|---|---|---|
| On the date on record | Sept 2025 | 0 | €281,400 | |
| By the median move (5 months) | Feb 2026 | 0 | €281,400 | |
| By 9 in 10 moves or less (16 months) | Jan 2027 | 2 | €281,400 | |
| By the longest move measured (18 months) | Mar 2027 | 4 | €281,400 |
The handover date on record has already passed. Ask the developer for the current date and the register status before you pay more.
No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.
Delays by marketMore buyer tools
Document checklistFind a project by permit or register numberLuxury residential complex, Vidal (Novigrad)
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/