Home / Projects / NEK HÁ / NEK HÁ: payment plan against late handover

NEK HÁ: payment plan against late handover

How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.

Data of 25 Nov 2026

Starting price on record: USD 289,790 (read 25 Nov 2026). Converted at the ECB reference rate of 25 Nov 2026. ecb.europa.eu

Handover on record: Q4 2026 (Web page, read 25 Nov 2026). Riviera Maya has too few measured moves, so the moves below are from all 20 later handover dates we measured across markets.

If handover movesHandoverMonths from todayPaid before handoverCost of the extra wait
On the date on recordDec 20261US$173,874
By the median move (5 months)May 20276US$173,874
By 9 in 10 moves or less (16 months)Apr 202817US$173,874
By the longest move measured (18 months)Jun 202819US$173,874

No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.

Delays by marketMore buyer tools

Document checklistFind a project by permit or register numberNEK HÁ

Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/

Protect my purchase