Mareva 2 the Oasis: payment plan against late handover

How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.

Data of 25 Nov 2026

No starting price on record: type the price you were quoted. Converted at the ECB reference rate of 24 Nov 2026. ecb.europa.eu

Handover on record: 28 Feb 2030 (Official register, read 23 Nov 2026). Moves below are from 18 later handover dates we measured in Dubai.

If handover movesHandoverMonths from todayPaid before handoverCost of the extra wait
On the date on recordFeb 203039
By the median move (5 months)Jul 203044
By 9 in 10 moves or less (12 months)Feb 203151
By the longest move measured (18 months)Aug 203157

No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.

Delays by marketMore buyer tools

Document checklistDeveloper timelineFind a project by permit or register numberMareva 2 the Oasis

Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/

Protect my purchase