Mandarin Oriental Residences, Grand Cayman: payment plan against late handover
How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.
Data of 25 Nov 2026
Starting price on record: USD 6,000,000 (read 5 Nov 2026). Converted at the ECB reference rate of 25 Nov 2026. ecb.europa.eu
Handover on record: 2028-Q1 (Developer site, read 5 Nov 2026). Cayman Islands has too few measured moves, so the moves below are from all 20 later handover dates we measured across markets.
| If handover moves | Handover | Months from today | Paid before handover | Cost of the extra wait |
|---|---|---|---|---|
| On the date on record | Mar 2028 | 16 | US$3,600,000 | |
| By the median move (5 months) | Aug 2028 | 21 | US$3,600,000 | |
| By 9 in 10 moves or less (16 months) | Jul 2029 | 32 | US$3,600,000 | |
| By the longest move measured (18 months) | Sept 2029 | 34 | US$3,600,000 |
No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.
Delays by marketMore buyer tools
Document checklistDeveloper timelineFind a project by permit or register numberMandarin Oriental Residences, Grand Cayman
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/