Home / Projects / Levia Residence / Levia Residence: payment plan against late handover
Levia Residence: payment plan against late handover
How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.
Data of 25 Nov 2026
Starting price on record: MYR 480,000 (read 17 Nov 2026). Converted at the ECB reference rate of 24 Nov 2026. ecb.europa.eu
Handover on record: 2027-Q3 (Listing portal, read 17 Nov 2026). Kuala Lumpur has too few measured moves, so the moves below are from all 20 later handover dates we measured across markets.
| If handover moves | Handover | Months from today | Paid before handover | Cost of the extra wait |
|---|---|---|---|---|
| On the date on record | Sept 2027 | 10 | MYR 288,000 | |
| By the median move (5 months) | Feb 2028 | 15 | MYR 288,000 | |
| By 9 in 10 moves or less (16 months) | Jan 2029 | 26 | MYR 288,000 | |
| By the longest move measured (18 months) | Mar 2029 | 28 | MYR 288,000 |
No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.
Delays by marketMore buyer tools
Document checklistDeveloper timelineFind a project by permit or register numberLevia Residence
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/