Shipping daily
Changelog →

Home / Projects / Las Palmas de Tamarindo / Las Palmas de Tamarindo: payment plan against late handover

Las Palmas de Tamarindo: payment plan against late handover

How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.

Data of 25 Nov 2026

Starting price on record: USD 297,357 (read 5 Nov 2026). Converted at the ECB reference rate of 24 Nov 2026. ecb.europa.eu

Handover on record: 2026-Q1 (Web page, read 5 Nov 2026). Costa Rica has too few measured moves, so the moves below are from all 20 later handover dates we measured across markets.

If handover movesHandoverMonths from todayPaid before handoverCost of the extra wait
On the date on recordMar 20260US$178,414
By the median move (5 months)Aug 20260US$178,414
By 9 in 10 moves or less (16 months)Jul 20278US$178,414
By the longest move measured (18 months)Sept 202710US$178,414

The handover date on record has already passed. Ask the developer for the current date and the register status before you pay more.

No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.

Delays by marketMore buyer tools

Document checklistFind a project by permit or register numberLas Palmas de Tamarindo

Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/

Protect my purchase