Home / Projects / Alto Mare / Alto Mare: payment plan against late handover

Alto Mare: payment plan against late handover

How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.

Data of 25 Nov 2026

Starting price on record: USD 104,343 (read 25 Nov 2026). Converted at the ECB reference rate of 25 Nov 2026. ecb.europa.eu

Handover on record: Q3 2027 (Web page, read 25 Nov 2026). Riviera Maya has too few measured moves, so the moves below are from all 20 later handover dates we measured across markets.

If handover movesHandoverMonths from todayPaid before handoverCost of the extra wait
On the date on recordSept 202710US$62,606
By the median move (5 months)Feb 202815US$62,606
By 9 in 10 moves or less (16 months)Jan 202926US$62,606
By the longest move measured (18 months)Mar 202928US$62,606

No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.

Delays by marketMore buyer tools

Document checklistFind a project by permit or register numberAlto Mare

Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/