619 Brickell by Nobu: payment plan against late handover
How long the money you pay before handover would wait if the date moved the way dates have moved in this market. Built from the moves we measured, not a forecast.
Data of 25 Nov 2026
No starting price on record: type the price you were quoted. Converted at the ECB reference rate of 25 Nov 2026. ecb.europa.eu
Handover on record: 2030 (Listing portal, read 12 Nov 2026). Miami has too few measured moves, so the moves below are from all 20 later handover dates we measured across markets.
| If handover moves | Handover | Months from today | Paid before handover | Cost of the extra wait |
|---|---|---|---|---|
| On the date on record | Dec 2030 | 49 | ||
| By the median move (5 months) | May 2031 | 54 | ||
| By 9 in 10 moves or less (16 months) | Apr 2032 | 65 | ||
| By the longest move measured (18 months) | Jun 2032 | 67 |
No promise about this project: past moves in a market do not say what one developer will do. The cost column is simple interest on the money paid before handover, for the extra months only.
Delays by marketMore buyer tools
Document checklistDeveloper timelineFind a project by permit or register number619 Brickell by Nobu
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/