Dubai fact sheet
One page on Dubai for buyers and advisers: 1,004 projects, what we hold on each key fact, handover years, delays we measured and the registers to check.
Data of 23 Nov 2026
Laid out for A4 paper; menus and buttons are left out.
Key facts we hold
| Field | Projects holding it | Share here | From an official register |
|---|---|---|---|
| Handover date | 991 / 1,004 | 99% | 968 |
| Permit or registration number | 987 / 1,004 | 98% | 810 |
| Units | 981 / 1,004 | 98% | 981 |
| Starting price | 834 / 1,004 | 83% | 662 |
| Developer legal entity | 986 / 1,004 | 98% | 936 |
| Escrow or deposit protection | 987 / 1,004 | 98% | 44 |
| Construction progress | 984 / 1,004 | 98% | 984 |
| Satellite reading (built-up share, first > last) | 7 / 1,004 | 1% | 0 |
| Official register entry | 983 / 1,004 | 98% | 983 |
| Court cases on record (developer) | 82 / 1,004 | 8% | 82 |
Dubai: handover year on record
991 of 1,004 projects in Dubai have a handover date on record.
| Handover year | Projects | Units (register) | Date from a register |
|---|---|---|---|
| 2025 or earlier | 2 | 506 (2 of 2 projects) | 100% |
| 2026 | 88 | 29,992 (84 of 88 projects) | 92% |
| 2027 | 389 | 111,675 (386 of 389 projects) | 98% |
| 2028 | 320 | 100,746 (317 of 320 projects) | 98% |
| 2029 | 137 | 51,109 (134 of 137 projects) | 99% |
| 2030 | 48 | 24,459 (47 of 48 projects) | 98% |
| 2031 or later | 7 | 5,533 (6 of 7 projects) | 86% |
Delays by market
- 18 of 468 projects we follow day by day had their handover date moved later (median 4.5 months).
- 18 projects have a handover date on record that has passed while the register shows building below 100%.
Official registers to check
- DLD Project Status Enquiry (dubailand.gov.ae): Permit or registration number, Official register entry checked 13 Nov 2026
- Project escrow account (dubailand.gov.ae): Escrow or deposit protection checked 13 Nov 2026
- Oqood (off-plan sale registration) (dubailand.gov.ae): Official register entry checked 13 Nov 2026
Best documented here
- Aykon City 3 10/10
- Alder at Park Five 9/10
- Arancia Yards by Beyond 9/10
- Aspirz 9/10
- Bayz 101 by Danube 9/10
Thinnest records here
- The Archive by Imtiaz 0/10
- Samana Downtown One 0/10
- Samana Barari Twin Towers 0/10
- Kore by Imtiaz 0/10
- Grand Polo Club & Resort 0/10
Source: https://kolaboro.com/data/markets/dubai/, data of 23 Nov 2026. Open data under CC BY 4.0.
DubaiHandover pipeline by yearDelays by market
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/