Look up the permit or licence number and the developer company on the official registers.
Our record: Permit number published: DLD project registrations 3600, 3606, 3607. Company: legal name published. Official registers for Dubai: DLD Project Status Enquiry.
Pay the reservation fee only into an account in the project's or an escrow bank's name, and get a receipt that names the unit.
Our record: Deposit protection stated by the developer. Official registers for Dubai: Project escrow account.
Have an independent lawyer read it: handover date, late-delivery penalty, refund terms and payment schedule.
Register the purchase with the official register where the market has one, and keep the proof.
Our record: Official registers for Dubai: Oqood (off-plan sale registration).
Tie each payment to a construction milestone and check the progress before you pay.
Follow the site: satellite images, register updates and changes to the published handover date.
Our record: Construction: not checked yet.
Compare the date in your contract with the date on record, and what the contract says if it is late.
Our record: Handover date on record: May 2029. In Dubai, 8 projects with a passed handover date: median 5 months late (historical record).
Inspect the unit with a snagging list before you accept the keys and pay the last instalment.
Make sure the title deed or final registration is issued in your name.
Project page · My checklist · A historical record from public sources, not a verdict about any developer.