Uda Land: every project by handover date
One timeline across all the developer's projects we track: the handover date on record, construction progress, starting price and every handover move we saw in our daily copies.
Data of 25 Nov 2026
Uda Land: 2 projects, 2 with a handover date on record, 0 of those dates already passed, 0 projects with a handover move in our daily copies.
2027 (1)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Taman Wakaf Seetee Aisah | Malaysia | 2027-08 Web page | 76.2% | MYR 299,991 |
2029 (1)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Eight & Eight Condominium | Malaysia | 2029-11 Web page | 23.85% | MYR 691,628 |
A move is a handover date that changed between two of our daily copies of the record; the date in brackets is when we saw it.
Uda LandDevelopers compared by register-confirmed factsCompare up to 4 developers side by side
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/