Home / Developers / Neinor Homes / Neinor Homes: every project by handover date
Neinor Homes: every project by handover date
One timeline across all the developer's projects we track: the handover date on record, construction progress, starting price and every handover move we saw in our daily copies.
Data of 25 Nov 2026
Neinor Homes: 39 projects, 7 with a handover date on record, 1 of those dates already passed, 0 projects with a handover move in our daily copies.
2026 (2)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Lagune Homes | Costa Blanca | 2026-Q3 Developer site | €379,000 | ||
| Bliss Homes | Costa del Sol | 2026-Q4 Developer site | €395,000 |
2027 (2)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Creative Homes Bulevar | Costa del Sol | 2027 Developer site | €292,000 | ||
| Etherna Homes | Costa del Sol | 2027 Developer site | €307,000 |
2028 (3)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Etherna Homes II | Costa del Sol | 2028-Q2 Developer site | €305,000 | ||
| NO|BA Homes V | Spain | 2028-Q2 Developer site | €360,500 | ||
| Creative Homes Bulevar III | Costa del Sol | 2028-Q4 Developer site | €344,000 |
No handover date on record (32)
A move is a handover date that changed between two of our daily copies of the record; the date in brackets is when we saw it.
Neinor HomesDevelopers compared by register-confirmed factsCompare up to 4 developers side by side
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/