Expo City Dubai: every project by handover date

One timeline across all the developer's projects we track: the handover date on record, construction progress, starting price and every handover move we saw in our daily copies.

Data of 25 Nov 2026

Expo City Dubai: 7 projects, 7 with a handover date on record, 1 of those dates already passed, 0 projects with a handover move in our daily copies.

2026 (1)

ProjectMarketHandover dateConstruction progressStarting priceHandover moves seen
Expo Valley (villas and townhouses)Dubai31 Jan 2026 Official register66%€841,993

2027 (2)

ProjectMarketHandover dateConstruction progressStarting priceHandover moves seen
Expo City Al Waha Residences 01Dubai15 Jun 2027 Official register65.79%€248,376
Expo City Al Waha Residences 02Dubai30 Jun 2027 Official register61.38%€496,751

2028 (1)

ProjectMarketHandover dateConstruction progressStarting priceHandover moves seen
Expo City Sidr ResidencesDubai31 Mar 2028 Official register25.02%€695,451

2029 (2)

ProjectMarketHandover dateConstruction progressStarting priceHandover moves seen
Expo Valley ViewsDubai31 Oct 2029 Official register0%€422,238
Expo Valley Views 2Dubai31 Oct 2029 Official register0%

2030 (1)

ProjectMarketHandover dateConstruction progressStarting priceHandover moves seen
Expo Valley Views 1Dubai30 Mar 2030 Official register0%

A move is a handover date that changed between two of our daily copies of the record; the date in brackets is when we saw it.

Expo City DubaiDevelopers compared by register-confirmed factsCompare up to 4 developers side by side

Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/