Home / Developers / Ellington Properties / Ellington Properties: every project by handover date
Ellington Properties: every project by handover date
One timeline across all the developer's projects we track: the handover date on record, construction progress, starting price and every handover move we saw in our daily copies.
Data of 25 Nov 2026
Ellington Properties: 24 projects, 22 with a handover date on record, 2 of those dates already passed, 3 projects with a handover move in our daily copies.
2026 (3)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| UH East by Ellington | Dubai | 30 Mar 2026 Official register | 62.75% | AED 900,000 | |
| UH West by Ellington | Dubai | 3 Mar 2026 Official register | 83.72% | AED 836,000 | |
| Hillmont Residences by Ellington | Dubai | 31 Dec 2026 Official register | 26.29% | AED 1,200,000 |
2027 (5)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| One River Point | Dubai | 9 Jun 2027 Official register | 35.43% | AED 2,300,000 | |
| Mercer House | Dubai | 31 Jul 2027 Official register | 18.11% | AED 1,100,000 | |
| Belmore Residences | Dubai | 31 Dec 2027 Official register | 6.53% | AED 1,500,000 | |
| Claydon House by Ellington | Dubai | 31 Dec 2027 Official register | 15.72% | AED 1,500,000 | |
| Riverton House | Dubai | 31 Dec 2027 Official register | 0% | AED 2,100,000 |
2028 (9)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| The Watercrest | Dubai | 31 Mar 2028 Official register | 2.2% | AED 6,400,000 | |
| Eaton Square | Dubai | 30 Jun 2028 Official register | 5.39% | ||
| The Hillgate | Dubai | 30 Jun 2028 Official register | 3.12% | AED 1,280,000 | |
| Belgravia Gardens | Dubai | 30 Sept 2028 Official register | 3.08% | AED 1,100,000 | |
| Costa Mare | Ras Al Khaimah | 2028-Q3 Developer site | |||
| Ellington Sands I | Dubai | 31 Dec 2028 Official register | 0.37% | AED 2,149,000 | 2028-Q2 > 31 Dec 2028 (18 Nov 2026) |
| Ellington Sands II | Dubai | 31 Dec 2028 Official register | 0.38% | AED 2,000,000 | |
| Eltiera Heights | Dubai | 31 Dec 2028 Official register | 3.01% | AED 2,000,000 | |
| The Highgrove | Dubai | 31 Dec 2028 Official register | 7% | AED 1,800,000 | 2027-Q4 > 31 Dec 2028 (18 Nov 2026) |
2029 (4)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Windsor House | Dubai | 31 Jul 2029 Official register | 3.08% | AED 1,200,000 | |
| Windsor House II | Dubai | 31 Jul 2029 Official register | 0.6% | AED 716,000 | |
| Eltiera Views | Dubai | 31 Dec 2029 Official register | 0% | AED 2,200,000 | |
| Portside Square | Dubai | 31 Dec 2029 Official register | 0% | AED 2,200,000 |
2031 (1)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| The Meriva Collection (Meriva Gardens / Meriva Signature) | Dubai | 31 Dec 2031 Official register | 0.1% | AED 2,700,000 | 2030-Q2 > 31 Dec 2031 (18 Nov 2026) |
No handover date on record (2)
| Project | Market | Handover date | Construction progress | Starting price | Handover moves seen |
|---|---|---|---|---|---|
| Soto Grande | Ras Al Khaimah | ||||
| The Highbury | Dubai | 80.03% | AED 850,000 |
A move is a handover date that changed between two of our daily copies of the record; the date in brackets is when we saw it.
Ellington PropertiesDevelopers compared by register-confirmed factsCompare up to 4 developers side by side
Method: values come from our published dataset, the DLD register mirror, our Sentinel-2 construction index and the court records we hold. The register list is the one on our registers page, each register probed by our checker. Not a verdict about any project or developer. How we verify a factData fileBuild script/registers/