BEGIN:VEVENT
UID:DXB-466-construction_start-1@kolaboro.com
DTSTAMP:20261118T000000Z
DTSTART;VALUE=DATE:20241130
DTEND;VALUE=DATE:20241201
SUMMARY:Verve City Walk: Construction start\, promised for November 2024
DESCRIPTION:Date published by the developer: November 2024.\nSource: https:
 //dubairealestateiq.com/project/verve-city-walk (read on 18 Nov 2026).\nRe
 cord with all sources: https://kolaboro.com/projects/verve-city-walk/#deli
 very\nThis is the developer's date\, not a confirmation by Kolaboro. A per
 iod is placed on its last day.
URL:https://kolaboro.com/projects/verve-city-walk/#delivery
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:DXB-466-handover-1@kolaboro.com
DTSTAMP:20261118T000000Z
DTSTART;VALUE=DATE:20280930
DTEND;VALUE=DATE:20281001
SUMMARY:Verve City Walk: Handover or completion\, promised for September 20
 28
DESCRIPTION:Date published by the developer: September 2028.\nSource: https
 ://dubairealestateiq.com/project/verve-city-walk (read on 18 Nov 2026).\nR
 ecord with all sources: https://kolaboro.com/projects/verve-city-walk/#del
 ivery\nThis is the developer's date\, not a confirmation by Kolaboro. A pe
 riod is placed on its last day.
URL:https://kolaboro.com/projects/verve-city-walk/#delivery