BEGIN:VCALENDAR
VERSION:2.0
PRODID:-//Kolaboro//Promised dates 1.0//EN
CALSCALE:GREGORIAN
METHOD:PUBLISH
X-WR-CALNAME:Marquis Vista: promised dates (Kolaboro)
X-WR-CALDESC:This is the developer's date\, not a confirmation by Kolaboro.
  A period is placed on its last day. https://kolaboro.com/projects/marquis
 -vista/#delivery
REFRESH-INTERVAL;VALUE=DURATION:P1D
X-PUBLISHED-TTL:P1D
BEGIN:VEVENT
UID:DXB-588-construction_start-1@kolaboro.com
DTSTAMP:20261123T000000Z
DTSTART;VALUE=DATE:20250630
DTEND;VALUE=DATE:20250701
SUMMARY:Marquis Vista: Construction start\, promised for June 2025
DESCRIPTION:Date published by the developer: June 2025.\nSource: https://du
 bairealestateiq.com/project/marquis-vista (read on 21 Nov 2026).\nRecord w
 ith all sources: https://kolaboro.com/projects/marquis-vista/#delivery\nTh
 is is the developer's date\, not a confirmation by Kolaboro. A period is p
 laced on its last day.
URL:https://kolaboro.com/projects/marquis-vista/#delivery
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:DXB-588-handover-1@kolaboro.com
DTSTAMP:20261123T000000Z
DTSTART;VALUE=DATE:20271231
DTEND;VALUE=DATE:20280101
SUMMARY:Marquis Vista: Handover or completion\, promised for December 2027
DESCRIPTION:Date published by the developer: December 2027.\nSource: https:
 //dubairealestateiq.com/project/marquis-vista (read on 21 Nov 2026).\nReco
 rd with all sources: https://kolaboro.com/projects/marquis-vista/#delivery
 \nThis is the developer's date\, not a confirmation by Kolaboro. A period 
 is placed on its last day.
URL:https://kolaboro.com/projects/marquis-vista/#delivery
TRANSP:TRANSPARENT
END:VEVENT
END:VCALENDAR