BEGIN:VEVENT
UID:DXB-196-construction_start-1@kolaboro.com
DTSTAMP:20261118T000000Z
DTSTART;VALUE=DATE:20260228
DTEND;VALUE=DATE:20260301
SUMMARY:Artistry Two Residences: Construction start\, promised for February
  2026
DESCRIPTION:Date published by the developer: February 2026.\nSource: https:
 //dubairealestateiq.com/project/artistry-two-residences (read on 17 Nov 20
 26).\nRecord with all sources: https://kolaboro.com/projects/artistry-two-
 residences/#delivery\nThis is the developer's date\, not a confirmation by
  Kolaboro. A period is placed on its last day.
URL:https://kolaboro.com/projects/artistry-two-residences/#delivery
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:DXB-196-handover-1@kolaboro.com
DTSTAMP:20261118T000000Z
DTSTART;VALUE=DATE:20290228
DTEND;VALUE=DATE:20290301
SUMMARY:Artistry Two Residences: Handover or completion\, promised for Febr
 uary 2029
DESCRIPTION:Date published by the developer: February 2029.\nSource: https:
 //dubairealestateiq.com/project/artistry-two-residences (read on 17 Nov 20
 26).\nRecord with all sources: https://kolaboro.com/projects/artistry-two-
 residences/#delivery\nThis is the developer's date\, not a confirmation by
  Kolaboro. A period is placed on its last day.
URL:https://kolaboro.com/projects/artistry-two-residences/#delivery